Scenario: Please read this scenario prior to answering the question Your role is that of a consultant to the Lead Enterprise Architect in a company…

Full set: 419 questions
Scenario: Please read this scenario prior to answering the question Your role is that of a consultant to the Lead Enterprise Architect in a company that develops wind turbines for use in wind farms. The company has three manufacturing facilities, one in North America, one in Asia, and one in Europe. Each of these facilities supplies the power industry in its region. The company recognizes that the long-term technical potential of wind energy can address the current global dependency on carbon fuels. In order to do so this will require wind turbines to be installed over large areas of higher wild resources. In particular, offshore wind farms can contribute substantially more energy than land stationed trubines. The research arm of the company has pioneered the development of an offshore wind turbine design, with an improved turbine blade and power system that will produce up to 20% more energy. This will allow the production of significantly more saleable energy. This new design is ready to go into production. The company has a mature Enterprise Architecture organization that is supported by a cross- functional Architecture Board and uses the TOGAF standard. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program. Recently, a pilot architecture project was completed at a single location that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Architecture Board approved the plan for immediate implementation at each plant. Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency. Refer to the Scenario You have been asked to recommend the best approach to address the Chief Engineer's concern. Based on TOGAF 9, which of the following is the best answer?
Answer options
A: You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract.You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs. Correct answer
B: You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract.You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
C: You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization.You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
D: You use the issued Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of the completed blade assembly at each location and develop change requirements if necessary.You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
Correct Answer:
A. You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract.You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
Explanation

This option correctly describes the activities within Phase G: Implementation Governance. The Chief Engineer's concern is about ensuring consistent implementation according to the defined architecture. The best approach is to use the existing Architecture Contracts as the basis for governance. This involves conducting formal Compliance Reviews at key milestones to check adherence to the architecture. Any deviations must be managed through a formal process, where the Architecture Board reviews the deviation and decides whether to grant a dispensation or require the project to conform. This ensures consistency while providing a controlled mechanism for exceptions.

Why Incorrect

B. This option is incorrect because the scenario explicitly states that the Architecture Contracts have already been developed, so creating new ones is not the next step.
C. This option is also incorrect as it starts by creating contracts that already exist. It also wrongly suggests that dispensations should be granted presumptively, undermining the goal of consistency.
D. This option incorrectly recommends modifying the Architecture Contract to allow customization, which is the opposite of the Chief Engineer's goal of a uniform process. Governance should enforce the standard, not change it for convenience.

References

- The Open Group, "TOGAF® Standard, Version 9.2," 2018, Section 13.2, "Phase G: Implementation Governance, Steps". Step 2 is "Conduct Compliance Assessments", which is the core of this answer.

- The Open Group, "TOGAF® Standard, Version 9.2," 2018, Section 44.3.4, "Architecture Governance". This section describes the role of compliance assessments in ensuring projects adhere to defined standards and architectures.

- The Open Group, "TOGAF® Standard, Version 9.2," 2018, Section 42.7, "Architecture Contracts". This section explains that contracts are used to govern the implementation project and are subject to compliance reviews. The concept of dispensations is a key part of this governance.