PGMP practice question 2 of 35
All of the following are resources that you will need to monitor and control in a program environment except for which one?
Full set: 452 questionsAccording to the Project Management Institute's (PMI) official standards, resources are the inputs required to perform program work. This includes team members, supplies, equipment, materials, and facilities. Staff members (A) and equipment (D) are explicitly defined as human and physical resources, respectively. While contracts (B) are managed within a program, they are legal instruments used in procurement to acquire resources or services, not resources themselves. However, quality (C) is fundamentally different; it is a performance characteristic, a conformance requirement, and a key performance indicator. It is a standard to be achieved, not a resource to be consumed or allocated, making it the correct exception.
A. Staff members: These are the primary human resources managed within the Program Resource Management performance domain.
B. Contracts: While not a resource, a contract is a tangible instrument for acquiring resources. Quality is a more abstract concept representing a performance standard, making it a better exception.
D. Equipment: This is a classic example of a physical resource that is identified, acquired, and managed throughout the program lifecycle.
1. Project Management Institute. (2017). The Standard for Program Management (4th ed.).
For Correct Answer (C): The Glossary defines a resource as "Team members
supplies
equipment
materials
and facilities" (p. 208). This definition excludes 'quality'. The Program Quality Management performance domain (Section 5.4
p. 77) treats quality as a set of processes for meeting stakeholder objectives
not as a consumable resource.
For Incorrect Options (A
D): The Program Resource Management performance domain (Section 5.5
p. 83) is explicitly concerned with "processes to identify
acquire
and manage the resources
" specifically citing human and physical resources (staff and equipment).
For Incorrect Option (B): The Program Procurement Management performance domain (Section 5.6
p. 89) covers the management of contracts to acquire external results
distinguishing them from the program's internal resources.
Keep practicing
Take the free PGMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PGMP practice questions
- Question 1You are the program manager of the NHQ Program. You will need to initiate six projects fo…
- Question 3A company is evaluating the implementation of enterprise resource planning (ERP) software…
- Question 4The program manager defines the program objectives, requirements, and develops a high-lev…
- Question 5Which of the following represents the duration of activities against a calendar?
- Question 6During the selection of source process, you assign certain points towards various categor…
- Question 7Which of the following can be used to help you or other project managers on future projec…