PGMP practice question 1 of 35
You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?
Full set: 452 questionsProjects within a program are initiated on an as-needed basis throughout the program's life cycle to achieve its strategic objectives. The initiation of components is a key activity within the Program Benefits Delivery phase, which is iterative. As the program progresses and delivers incremental benefits, new projects may be authorized and started to build upon previous results or address emerging requirements. This dynamic process continues until the program has delivered its intended benefits and is ready to transition into the Program Closure phase. Therefore, project initiation is not a single event but occurs whenever necessary during the active delivery stages of the program.
B: "Program execution" is a general term. The specific PMI phase is Program Benefits Delivery, where projects are initiated iteratively, not as a single execution event. C: The Program Initiation phase focuses on authorizing the program itself and developing the program charter, not on initiating its individual component projects. D: Program Planning involves developing the program management plan and roadmap, which identifies components, but the formal authorization and initiation of projects occur later.
1. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 1.5.3.2, Program Benefits Delivery Phase, p. 21. "During this phase, program components are initiated, planned, executed, and transitioned..."
2. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Figure 1-6, Program Management Performance Domains and Program Life Cycle Phases, p. 20. This figure illustrates that component initiation and planning are activities that occur within the Program Benefits Delivery phase.
3. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 3.4.3, Program Benefits Delivery Phase, p. 50. "During this phase, the program manager and the program governance board provide oversight and integrate the work being performed by the program components... New components may be initiated, planned, and authorized..."
Keep practicing
Take the free PGMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PGMP practice questions
- Question 2All of the following are resources that you will need to monitor and control in a program…
- Question 3A company is evaluating the implementation of enterprise resource planning (ERP) software…
- Question 4The program manager defines the program objectives, requirements, and develops a high-lev…
- Question 5Which of the following represents the duration of activities against a calendar?
- Question 6During the selection of source process, you assign certain points towards various categor…
- Question 7Which of the following can be used to help you or other project managers on future projec…
