PMI-CAPM practice question 1 of 35
An input to the Estimate Activity Resources process is:
Full set: 1,329 questionsThe Estimate Activity Resources process involves estimating the team resources and the type and quantities of materials, equipment, and supplies necessary to perform project work. The resource calendar is a critical input because it identifies the working days, shifts, and availability of specific resources. This information directly influences the estimation of the quantity and duration for which a resource is needed, ensuring the estimates are realistic and aligned with resource constraints.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute. Section 9.2.1.2, Project Documents, p. 315.
2. Shtub, A. (2016). Project Management: Processes, Methodologies, and Economics (3rd ed.). Pearson. Chapter 5, "The Project and the Organization," discusses resource availability and calendars as fundamental components for planning. (Note: This aligns with the principles taught in university-level project management courses).
Keep practicing
Take the free PMI-CAPM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-CAPM practice questions
- Question 2When can pre-assignment of project team members occur?
- Question 3Which tool or technique of Plan Quality involves comparing actual or planned practices to…
- Question 4A project lifecycle is defined as:
- Question 5Change request status updates are an output of which process?
- Question 6What type of reward can hurt team cohesiveness?
- Question 7Which of the following is a set of interrelated actions and activities performed to achie…