PMI-CAPM practice question 1 of 35

An input to the Estimate Activity Resources process is:

Full set: 1,329 questions
Answer options
A: Activity resource requirements.
B: Published estimating data.
C: Resource calendars. Correct answer
D: Resource breakdown structure (RBS).
Correct Answer:
C. Resource calendars.
Explanation

The Estimate Activity Resources process involves estimating the team resources and the type and quantities of materials, equipment, and supplies necessary to perform project work. The resource calendar is a critical input because it identifies the working days, shifts, and availability of specific resources. This information directly influences the estimation of the quantity and duration for which a resource is needed, ensuring the estimates are realistic and aligned with resource constraints.

References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute. Section 9.2.1.2, Project Documents, p. 315.

2. Shtub, A. (2016). Project Management: Processes, Methodologies, and Economics (3rd ed.). Pearson. Chapter 5, "The Project and the Organization," discusses resource availability and calendars as fundamental components for planning. (Note: This aligns with the principles taught in university-level project management courses).