PMI-CAPM practice question 5 of 35
Change request status updates are an output of which process?
Full set: 1,329 questionsThe Perform Integrated Change Control process is responsible for reviewing all change requests, evaluating their impact, and then approving, rejecting, or deferring them. A primary output of this decision-making process is the updated status of these change requests. This status is formally recorded in the change log, which is a project document updated as part of this process. This ensures that the disposition of all change requests is communicated to relevant stakeholders.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute. Section 4.6, Perform Integrated Change Control, p. 113.
2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute. Section 4.6.3.2, Change Log, p. 120. The text states, "The status of all change requests...are recorded in the change log."
3. Vargas, R. V. (2019). Practical Guide to the PMBOK® Guide (6th ed.). CRC Press. This academic text, which analyzes the PMBOK, confirms that the change log, which contains the status of change requests, is an output of the Perform Integrated Change Control process. (Chapter 4, Integration Management).
Keep practicing
Take the free PMI-CAPM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-CAPM practice questions
- Question 1An input to the Estimate Activity Resources process is:
- Question 2When can pre-assignment of project team members occur?
- Question 3Which tool or technique of Plan Quality involves comparing actual or planned practices to…
- Question 4A project lifecycle is defined as:
- Question 6What type of reward can hurt team cohesiveness?
- Question 7Which of the following is a set of interrelated actions and activities performed to achie…