The Kaizen feedback loop can be summarized as:
Full set: 193 questionsThe Kaizen (Deming) feedback cycle that underpins continuous improvement is Plan-Do-Study-Act (PDSA). Teams plan a change, do (implement) it, study the results, and act by adopting or abandoning the change, thereby closing the learning loop.
A. “Monitor” replaces “Study”; not the standard Deming/Kaizen wording.
B. Sequence and verbs do not match the recognized PDSA model.
C. “Implement” and “Demo” deviate from the established Kaizen terminology.
1. Liker, J.K. “The Toyota Way”, McGraw-Hill, 2004, pp. 241–242 (Kaizen and PDSA).
2. Ambler, S.W. & Lines, M. “Choose Your WoW!”, PMI Press, 2020, p. 376 (Kaizen continuous-improvement loop).
Keep practicing
Take the free PMI-DASSM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-DASSM practice questions
- Question 1DA guidelines includes using design thinking. The primary advantage of design thinking is…
- Question 2Why is the coordination meeting important for a project team?
- Question 4What is the role of the product owner?
- Question 5During which iterative ceremony should someone obtain feedback?
- Question 6What are the three phases common across project life cycles?
- Question 7A scrum master needs to set up a team for a long-term project that has the potential for …