Which of the following is one of the process goals in the transition stage?
Full set: 193 questionsDuring DAD’s Transition phase, the team ensures the solution can operate in production; the dedicated Transition process goal is “Ensure Production Readiness.”
A. “Produce a Potentially Consumable Solution” is a Construction-phase goal.
B. “Develop Common Vision” belongs to the Inception phase.
D. “Address Risk” is addressed primarily in Inception, not Transition.
1. PMI. “Choose Your WoW!,” 2nd ed., 2020, Appendix A, Table A-1 – Process goals by life-cycle phase.
2. Ambler, S. & Lines, M. “Disciplined Agile Delivery,” IBM Press, 2012, pp. 135-138 – Transition phase goals, including Ensure Production Readiness.
Keep practicing
Take the free PMI-DASSM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-DASSM practice questions
- Question 1DA guidelines includes using design thinking. The primary advantage of design thinking is…
- Question 2Why is the coordination meeting important for a project team?
- Question 4What is the role of the product owner?
- Question 5During which iterative ceremony should someone obtain feedback?
- Question 6What are the three phases common across project life cycles?
- Question 7A scrum master needs to set up a team for a long-term project that has the potential for …