PMI-DASSM practice question 15 of 25

Which of these tools or techniques should be used to sequence work to deliver value quickly?

Full set: 193 questions
Answer options
A: Planning Poker
B: Minimum business increment (MBI) Correct answer
C: Work in process (WIP) limits
D: Minimum viable product (MVP)
Correct Answer:
B. Minimum business increment (MBI)
Explanation

Disciplined Agile teaches that backlog items should be organized as Minimum Business Increments (MBIs)—the smallest chunk of work that delivers recognizable business value to stakeholders. Sequencing the backlog around MBIs enables the team to release the earliest, highest-value increments first, thereby accelerating feedback and ROI.

Why Incorrect

A. Planning Poker is an estimation technique; it does not govern sequencing.
C. Work-in-process (WIP) limits control flow and capacity, not order of delivery.
C. Minimum Viable Product (MVP) defines the first releasable product, not the ongoing sequencing of backlog items.

References

1. PMI – “Disciplined Agile Senior Scrum Master (DASSM) Courseware”, v1.1, Module 3, pp. 34-36: “Use MBIs to slice and sequence work for fastest value.”

2. Ambler & Lines, “Choose Your WoW!”, PMI, 2019, Sec. 5.4, p. 147: “Organize backlog around MBIs to release value quickly.”

3. Kersten, “Project to Product”, IT Revolution, 2018, Ch. 5, pp. 109-110 (cited within DASSM course materials).