PMI-PBA practice question 17 of 30

A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?

Full set: 200 questions
Answer options
A: Request that the project manager identify all affected project stakeholders.
B: Provide all signed-off project documentation to the stakeholders for information purposes only.
C: Engage all stakeholders early in the requirements gathering phase to define acceptance criteria. Correct answer
D: Solicit feedback and add requirements to the project backlog.
Correct Answer:
C. Engage all stakeholders early in the requirements gathering phase to define acceptance criteria.
Explanation

To ensure the satisfaction of a new stakeholder group, they must be actively and proactively involved. Engaging them early in the process to help define the requirements and, crucially, the acceptance criteria for those requirements, is the most effective approach. This ensures that the solution is built to meet their specific, agreed-upon definition of success, directly linking the project's output to their satisfaction.

Why Incorrect

A. Identifying stakeholders is a necessary first step, but it does not, by itself, ensure their satisfaction. Engagement and action are required.
B. Providing documentation for information only is a passive, one-way communication method that does not foster engagement or ensure their needs are met.
D. Soliciting feedback and adding requirements is a good practice, but defining acceptance criteria (Option C) is more comprehensive as it establishes the test for success.

References

1. Project Management Institute. (2015). Business Analysis for Practitioners: A Practice Guide. Section 6.4, Determine Acceptance and Evaluation Criteria, p. 98. This section highlights that acceptance criteria are defined early and are critical for gaining stakeholder agreement on what constitutes a successful outcome.

2. Project Management Institute. (2017). The PMI Guide to Business Analysis. Section 5.2, Identify and Analyze Stakeholders, p. 98. The guide emphasizes that understanding stakeholder expectations and acceptance criteria is a key outcome of stakeholder analysis and is fundamental to project success.