PMI-PBA practice question 24 of 30

During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product's functions and requirements. The business analyst struggles with facilitating the group to reach an agreement. What should the business analyst have defined to avoid this?

Full set: 200 questions
Answer options
A: Communications approach in the business analysis plan
B: Decision-making process in the project management plan
C: Decision-making process in the business analysis plan Correct answer
D: Communications approach in the project management plan
Correct Answer:
C. Decision-making process in the business analysis plan
Explanation

The business analysis plan should define the decision-making process, including who has authority to make decisions, how conflicts will be resolved, and what consensus mechanisms will be used. This is essential for managing stakeholder disagreements during requirements activities. Having this defined beforehand provides the business analyst with established protocols to navigate conflicting priorities and reach agreements efficiently.

Why Incorrect

A. Communications approach addresses how information flows but doesn't resolve decision conflicts.

B. Project management plan's decision-making process covers project-level decisions, not requirements-specific conflicts.

D. Communications approach in project management plan is too broad and doesn't address requirements workshop facilitation.

References

1. PMI (2015). Business Analysis for Practitioners: A Practice Guide. Project Management Institute, pp. 38-40 (Business Analysis Planning section on decision-making processes).

2. IIBA (2015). A Guide to the Business Analysis Body of Knowledge (BABOK Guide) Version 3.0. International Institute of Business Analysis, Section 3.1.4 (Plan Business Analysis Approach - Decision Making).

3. PMI (2017). The PMI Guide to Business Analysis. Project Management Institute, Chapter 4, pp. 89-91 (Planning - Stakeholder Engagement and Decision Rights).

References

1. PMI (2015). Business Analysis for Practitioners: A Practice Guide. Project Management Institute, pp. 38-40 (Business Analysis Planning section on decision-making processes).

2. IIBA (2015). A Guide to the Business Analysis Body of Knowledge (BABOK Guide) Version 3.0. International Institute of Business Analysis, Section 3.1.4 (Plan Business Analysis Approach - Decision Making).

3. PMI (2017). The PMI Guide to Business Analysis. Project Management Institute, Chapter 4, pp. 89-91 (Planning - Stakeholder Engagement and Decision Rights).

Scroll to Top