PMI-PBA practice question 21 of 30
The document that defines the process for managing requirements revisions is the:
Full set: 200 questionsThe change management plan is a subsidiary plan of the overall project management plan. Its specific purpose is to establish the process for managing and controlling changes. This includes how revisions to requirements are submitted, evaluated for impact, approved or rejected, and then implemented and communicated. It provides the formal framework for handling all modifications to agreed-upon requirements throughout the project lifecycle.
A. The project management plan is a high-level, composite document; the change management plan is the specific component that details the revision process.
C. The communications management plan defines how, when, and by whom project information will be administered and disseminated, not the process for changing requirements.
D. The scope management plan defines how scope is defined, validated, and controlled, but the specific process for handling change requests falls under the change management plan.
Project Management Institute. (2017). The PMI Guide to Business Analysis. Section 6.6.2.1, p. 210. This section explicitly lists the "Change control process" as a key component of the business analysis plan or a separate change management plan.
Project Management Institute. (2015). Business Analysis for Practitioners: A Practice Guide. Section 5.6, p. 100. This section, "Manage Changes to Requirements," describes the need for a defined process to handle changes, which is documented in the change management plan.
Keep practicing
Take the free PMI-PBA practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-PBA practice questions
- Question 1A project team has completed the system use cases along with accompanying screen mockups.…
- Question 2Which of the following tools will help facilitate the decision-making process when stakeh…
- Question 3Which of the following is the best approach to enable developers and product owners to be…
- Question 4A business analyst is planning the business analysis activities for a new payroll project…
- Question 5What should a business analyst do after discovering that two solution requirements confli…
- Question 6Which of the following techniques is used to identify ambiguous or unverifiable requireme…
