PMI-PBA practice question 26 of 30

Which document best provides the boundaries for product development?

Full set: 200 questions
Answer options
A: Scope definition
B: Requirements baseline Correct answer
C: Project plan
D: Scope document
Correct Answer:
B. Requirements baseline
Explanation

The requirements baseline is the agreed-upon and approved set of requirements for a product, release, or iteration. Once established, it serves as the formal basis for development, testing, and scope management. Any subsequent changes must go through a formal change control process. Therefore, the requirements baseline acts as the definitive boundary for product development, clearly defining what is in scope for the development team to build. While the scope document defines the project's boundaries, the requirements baseline provides the specific, detailed boundaries for the product itself.

Why Incorrect

A. Scope definition is a broader description of project boundaries, while the requirements baseline contains the specific, approved details of the product to be built.
C. The project plan is a comprehensive document covering many aspects (schedule, cost, etc.); the requirements baseline is the specific component that defines the product scope.
D. The scope document defines the project's scope (the work to be done), whereas the requirements baseline defines the product's scope (the features to be built).

References

Project Management Institute. (2017). The PMI Guide to Business Analysis. Glossary, p. 368. (Defines requirements baseline as "The approved version of the requirements that can be changed only through formal change control procedures and is used as a basis for comparison.").

Project Management Institute. (2017). The PMI Guide to Business Analysis. Section 6.4.2.1, "Requirements Baseline," p. 196. (This section states the baseline represents the agreed-upon requirements that the project team is committed to delivering).