PMP practice question 7 of 35
During the execution phase of a major infrastructure project, your team uncovers a significant risk that could impact the project schedule by 4…
Full set: 230 questionsDomain Process
According to PMI standards, when a new risk is identified during project execution, the project manager must first document it in the risk register and facilitate a structured analysis to determine its probability and impact. Skipping analysis to appease a sponsor's demand for speed or relying on a majority vote violates the standard risk management process. By assessing the risk's characteristics and root causes collaboratively, the project manager ensures that any subsequent response strategy (mitigate, accept, monitor) aligns with the project's approved risk thresholds and constraints, enabling an evidence-based decision.
Option A: Implementing mitigation without formal analysis bypasses the risk management plan and fails to evaluate the actual probability, impact, or cost-effectiveness of the response.
Option C: Assuming a newly discovered risk is implicitly accepted is incorrect; all new risks must be formally documented, analyzed, and managed throughout the project lifecycle.
Option D: Escalating to the sponsor without first analyzing the risk and formulating recommendations abdicates the project manager's responsibility to manage project risks effectively.
1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition. Section 2.8 (Uncertainty Performance Domain), pp. 119-122. (Details the necessity of evaluating threats and opportunities continuously throughout the project lifecycle).
2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Section 11.3 (Perform Qualitative Risk Analysis), pp. 419-427. (Specifies the process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact).
3. Project Management Institute. (2009). Practice Standard for Project Risk Management. Chapter 6 (Perform Qualitative Risk Analysis), pp. 27-32. (Provides the framework for structured risk assessment and decision-making based on organizational thresholds).
Keep practicing
Take the free PMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMP practice questions
- Question 1The project manager is preparing for the kickoff meeting of a project that follows a 'pla…
- Question 2Health Records Modernization at Hospital Case Study A project manager led a health record…
- Question 4A project manager is leading a project focused on developing a machine learning platform.…
- Question 5A project manager is leading an iterative project to develop a very innovative product. H…
- Question 6A team is using a predictive model to determine possible cost overrun scenarios for a dis…
- Question 8As part of a restructuring effort, a company has transitioned from a projectized to a fun…
