10 free PMP exam-style questions for Project Management Professional, with answers, explanations and source references.

Last updated

Full set: 230 questions

Domain Business Environment

The project manager is preparing for the kickoff meeting of a project that follows a 'plan the work and work the plan' style. Upon studying the project charter, the project manager realizes that the project objectives will have to undergo frequent changes throughout the project. What should the project manager to do?
Answer options

Domain Business Environment

Health Records Modernization at Hospital Case Study A project manager led a health records modernization project at a hospital with a project budget of $US5 million and an 18-month timeline. The project involved multiple stakeholder groups including medical, administrative, and IT staff; board members; patients; insurance companies; external vendors; regulatory bodies; and union representatives. Stakeholder management was complex and a major undertaking for the project manager, but it was critical to achieve a positive project outcome. When the project started, the project manager conducted stakeholder analysis, using the information to create both a power/interest and an influence/impact matrix. The analysis showed that while the hospital board members and regulatory bodies had high power but moderate interest, the medical staff (doctors and nurses) had both high influence and high impact on the project. Administrative staff showed high interest but lower power, while patients and insurance companies had moderate interest and varying levels of influence. Based on the analysis, the project manager created a stakeholder engagement strategy that documented expectations, communication preferences, and influence levels in a stakeholder register. The project manager also made a RACI (responsible, accountable, consulted, informed) chart to show roles and responsibilities; and created communication channels and frequency for each stakeholder group, an issue escalation system, and a feedback system for continuous stakeholder input. To execute the modernization process of health records, the project manager realized that medical staff members would need to change their daily workflows. To facilitate change management for these stakeholders, the project manager created a clinical advisory committee, appointed department-specific ''champions,'' created focus groups for requirements gathering, started a training program, and developed key performance indicators (KPIs) to measure satisfaction. During project execution, several challenges emerged. The doctors expressed concerns about the system's impact on patient care, the nurses' union raised workload concerns, the IT department faced resource constraints, the insurance companies requested additional features, and the administrative staff worried about data security. The project manager responded to these challenges by increasing the frequency of stakeholder meetings, implementing a change management program, creating a beta system for stakeholder testing, developing contingency plans for various stakeholder scenarios, and establishing an issue resolution process. Despite these mitigation efforts, the medical staff required additional training, leading to a change request for a 2-month extension and a 10% budget increase. The board of directors approved this to help ensure high adoption and satisfaction rates among staff members. The project helped establish new good practices in future programs for stakeholder management in the organization's project management office (PMO). The documented lessons learned became a reference for future projects of similar scope and complexity. How should the project manager approach managing the regulatory bodies' requirements for the health records associated with this project? (Refer to the Health Records Modernization at Hospital Case Study exhibit.)
Answer options

Domain Process

FILL IN THE BLANK You are in the planning phase of a complex project with stakeholders from five different departments, each with competing priorities. To ensure alignment and obtain explicit commitment to the project's objectives and ground rules, you conduct a series of structured meetings with key stakeholder groups. What specific technique or mechanism should you use to formally document and secure stakeholder agreement on project goals, roles, and behavioral expectations?

Domain Business Environment

A project manager is leading a project focused on developing a machine learning platform. Midway through the project, the project manager learns of a new regulatory policy that will significantly change the way data is stored, processed, and manipulated. What should the project manager do?
Answer options

Domain People

A project manager is leading an iterative project to develop a very innovative product. However, a group of stakeholders are hesitant because the high complexity of the product involves many business rules. What should the project manager do?
Answer options

Domain Process

A team is using a predictive model to determine possible cost overrun scenarios for a disruptive technology project. The data being used is pooled from various projects implemented within the organization. What should the project manager do to increase accuracy?
Answer options

Domain Process

During the execution phase of a major infrastructure project, your team uncovers a significant risk that could impact the project schedule by 4 weeks. The risk has not been identified in your risk register. Two team members strongly advocate for immediate mitigation action; one other team member believes the risk is overblown and wants to monitor it. Your sponsor wants a quick decision. How should you proceed?
Answer options

Domain People

As part of a restructuring effort, a company has transitioned from a projectized to a functional organization. The project manager is concerned that the team members will become disengaged from their work on the current project because they are now reporting to a functional manager. What should the project manager do?
Answer options

Domain Process

FILL IN THE BLANK Your project is in execution phase with a planned value of $500,000 and an earned value of $400,000. Your actual costs to date are $420,000. You need to calculate the cost performance index (CPI) to evaluate team efficiency and forecast project costs. What is the CPI?

Domain Process

A project manager is completing a project that required machinery from several different vendors. Similar projects in the future may require the project manager to use the same vendors again; however, the quality and performance of the vendor products varied, creating project risk. What should the project manager do to facilitate the success of future projects?
Answer options
Question 1 of 10
Browse PMI exams

Exam domains

What the PMP practice set covers

Every question in this set is mapped to one of 3 exam domains. Check the official exam outline for the current domain weights.

People

2 of the 10 free questions

Process

5 of the 10 free questions

Business Environment

3 of the 10 free questions

Study resources

PMP study guides and comparisons

Go deeper than the practice questions: certification comparisons, study plans, and career context for PMP.

All guides

Source context

How this practice set is maintained

Maintained by the CertMage content team, this page loads questions from the exam dataset connected to its preparation resource. When an answer includes a supporting reference, it is shown with that answer so you can review the underlying vendor documentation.

Certification objectives, interfaces, and vendor services can change. Verify important details against the provider's current exam guide and documentation before your exam.

Scroll to Top