PMP practice question 10 of 35
A project manager is completing a project that required machinery from several different vendors. Similar projects in the future may require the project manager to use the same vendors again; however, the quality and performance of the vendor products varied, creating project risk. What should the project manager do to facilitate the success of future projects?
Full set: 230 questionsDomain Process
In PMI methodology, evaluating and documenting vendor performance is a critical activity during the Control Procurements process. By documenting the vendors' performance regarding quality, delivery time, and overall compliance, the project manager updates the Organizational Process Assets (OPAs). These updated OPAs, specifically vendor performance evaluations and lessons learned registers, become invaluable inputs for future projects during the Plan Procurement Management process. This historical data allows future project managers to make informed decisions, select high-performing vendors, and proactively mitigate risks associated with poor quality or delayed delivery, directly addressing the variance experienced in the current project.
Option A: Negotiating future prices is premature without a defined future project scope and does not address the historical quality and performance risks.
Option C: Updating contact information is a basic administrative task that fails to capture the critical performance data needed to mitigate future quality risks.
Option D: Demanding better future performance without an active contract is ineffective; internal documentation (OPAs) is the standard PMI method to guide future vendor selection.
1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 12.3.3.3 Organizational Process Assets Updates (Vendor performance evaluation documentation), pp. 499-500.
2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (7th ed.). Section 2.8.2.4 Procurement (Procurement closure and performance reviews), p. 75.
Keep practicing
Take the free PMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMP practice questions
- Question 1The project manager is preparing for the kickoff meeting of a project that follows a 'pla…
- Question 2Health Records Modernization at Hospital Case Study A project manager led a health record…
- Question 4A project manager is leading a project focused on developing a machine learning platform.…
- Question 5A project manager is leading an iterative project to develop a very innovative product. H…
- Question 6A team is using a predictive model to determine possible cost overrun scenarios for a dis…
- Question 7During the execution phase of a major infrastructure project, your team uncovers a signif…
