PMP practice question 11 of 35

During daily team coordination meetings, team members constantly ask which tasks they should focus on first. How should the project manager ensure the team is fully productive?

Full set: 230 questions

Domain Process

Answer options
A: Work with the product owner to ensure the product backlog is prioritized Correct answer
B: Review the project backlog during the team’s coordination meeting
C: Encourage team members to prioritize the product backlog
D: Ensure team members are working according to the project management plan
Correct Answer:
A. Work with the product owner to ensure the product backlog is prioritized
Explanation

In Agile frameworks, the product owner is solely responsible for prioritizing the product backlog to maximize the value delivered by the development team. The team's confusion about task priority indicates a potential gap in backlog refinement or prioritization. The project manager, acting as a facilitator or scrum master, should collaborate with the product owner to ensure the backlog is properly ordered. A well-prioritized backlog provides the clarity the team needs to be productive and self-organizing, directly addressing the root cause of their question. This ensures the team is always working on the most valuable items.

Why Incorrect

B. The daily coordination meeting is for synchronization, not for backlog review. This activity should happen during backlog refinement or sprint planning events.
C. The development team does not prioritize the product backlog; this is the accountability of the product owner who represents the business and customer needs.
D. In an adaptive environment, the team works from a prioritized backlog, not a static project management plan for daily tasks. The plan provides guidance, not task-level priority.

References

1. Project Management Institute. (2017). Agile Practice Guide. Section 4.2.2, p. 41. "The product owner is responsible for guiding the direction of the product... Product backlog management includes: ... Ordering the product backlog items."

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition. Section 2.7.2, p. 98. "The product owner is responsible for maximizing the value of the product resulting from the work of the team."

Scroll to Top