PPM-001 practice question 3 of 35

Formal written correspondence with the customer is required when:

Full set: 650 questions
Answer options
A: Defects are detected.
B: The customer requests additional work not covered under contract. Correct answer
C: The project has a schedule slippage that includes changes to the critical path.
D: The project has cost overruns.
Correct Answer:
B. The customer requests additional work not covered under contract.