PPM-001 practice question 6 of 35

The Java development of a project is outsourced to Indi a. The project schedule is starting to slip. What is the LEAST likely cause of the slippage?

Full set: 650 questions
Answer options
A: Lack of competent programmers Correct answer
B: Cultural influences
C: Internationalization
D: Communication
Correct Answer:
A. Lack of competent programmers