PRACTITIONER-DEPLOYMENT-MANAGEMENT practice question 13 of 25

When establishing deployment approaches, what is a key consideration for minimizing service disruption?

Full set: 140 questions
Answer options
A: Training end-users extensively before deployment
B: Deploying changes only during business hours
C: Conducting a thorough impact assessment of the changes Correct answer
D: Implementing the changes without a rollback plan
Correct Answer:
C. Conducting a thorough impact assessment of the changes
Explanation

A thorough impact assessment is a foundational activity in planning any deployment. It identifies potential risks and negative effects on services, users, and business processes. By understanding these impacts beforehand, the deployment team can create mitigation plans, schedule the deployment appropriately, and design the deployment approach (e.g., phased, big bang) specifically to minimize or avoid service disruption. This proactive analysis is the most critical step in ensuring a smooth transition and maintaining service stability.

Why Incorrect

A. Training is important for user adoption but does not directly minimize the technical or service-level disruption caused by the deployment itself.
B. Deploying during business hours typically maximizes, rather than minimizes, service disruption for the majority of users.
D. A rollback plan is essential for recovering from a failed deployment and is a key part of minimizing the duration of any potential disruption.

References

1. AXELOS. (2020). ITIL® 4 Practitioner: Deployment Management. TSO (The Stationery Office). Section 4.2.2, "Planning deployments," emphasizes that understanding the impact of the deployment on stakeholders is a key planning activity.

2. AXELOS. (2019). ITIL® 4 Foundation. TSO (The Stationery Office). Section 5.2.5, "Change Enablement," discusses the importance of assessing risks and impacts before deploying changes.