PRINCE2-FOUNDATION practice question 17 of 35
Which is a definition of management?
Full set: 478 questionsManagement in a project context involves the cycle of planning, delegating, monitoring, and controlling activities to achieve objectives. 'Instructing the execution of tasks in line with agreed ways of working' is a direct reflection of the delegating, monitoring, and controlling aspects of management. The project manager directs the team managers or team members to perform the work packages as defined, ensuring alignment with established project controls and standards. This is a core function of day-to-day project management.
B. Translating stakeholder requirements into quality criteria is a specific activity within the quality practice, not a general definition of management.
C. Assigning people to multiple projects is typically a function of corporate, programme, or portfolio management, not project-level management.
D. Defining, assuring, and accepting products is a shared responsibility, with the project board ultimately accepting products, not a definition of management itself.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office).
- Appendix C, "Glossary," p. 388: Defines management as "The process of planning, delegating, monitoring, and controlling all aspects of a project... to achieve the project objectives." Option A is a practical application of this definition.
- Section 10.1, "The project manager," p. 88: Describes the project manager's responsibility for "day-to-day management of the project."
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?