PRINCE2-FOUNDATION practice question 35 of 35

Which is shown in a product breakdown structure?

Full set: 478 questions
Answer options
A: Management stages, major products and control points
B: In which order the products should be created
C: The major products that are to be developed in a plan Correct answer
D: What resources are required to develop the products
Correct Answer:
C. The major products that are to be developed in a plan
Explanation

A product breakdown structure (PBS) is a hierarchical diagram showing all the products that will be created by a plan. It decomposes the final product into its major constituent products, which are then broken down further into their components. The PBS provides a complete, hierarchical view of what the project will produce, forming the foundation for product-based planning. It does not show dependencies, sequence, or resource requirements; its sole purpose is to identify and structure the products within the scope of the plan.

Why Incorrect

A. Management stages and control points are elements of a project plan's schedule, not a product breakdown structure, which focuses only on deliverables.
B. The order of creation and dependencies between products are shown in a product flow diagram, which is a subsequent step in product-based planning.
D. Resource requirements are determined during estimating and scheduling activities after the products have been identified, not within the product breakdown structure itself.

References

- AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Section 8.3.1, Figure 8.2, pp. 88-89.

- AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Appendix G, Glossary of terms, p. 396.