PRINCE2-FOUNDATION practice question 32 of 35

Which statement defines a risk?

Full set: 478 questions
Answer options
A: A certain event occurring in the future that will have a negative impact on the project's objectives
B: An event that has already occurred that the Project Manager must deal with immediately
C: An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives Correct answer
D: An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
Correct Answer:
C. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
Explanation

PRINCE2 defines a risk as 'an uncertain event or set of events that, should it or they occur, will have an effect on the achievement of objectives'. This definition emphasizes uncertainty and the potential impact on project objectives. The effect can be positive (an opportunity) or negative (a threat). This definition is fundamental to the PRINCE2 risk management approach, which addresses both threats and opportunities throughout the project lifecycle.

Why Incorrect

A. A risk is uncertain, not certain. A certain event is a fact or a planned activity. Also, risks can have a positive impact (opportunities), not just a negative one.
B. An event that has already occurred is classified as an issue or a problem, not a risk. Risk management is a proactive process dealing with future uncertainty.
D. Escalation to the Project Board is a potential response to a risk if it breaches tolerance, not part of the definition of what a risk is.

References

- AXELOS. (2023). Managing Successful Projects with PRINCE2 7. TSO (The Stationery Office). Glossary, p. 411.

- AXELOS. (2023). Managing Successful Projects with PRINCE2 7. TSO (The Stationery Office). Chapter 12, Section 12.1, p. 156.