Which statement defines a risk?
Full set: 478 questionsPRINCE2 defines a risk as 'an uncertain event or set of events that, should it or they occur, will have an effect on the achievement of objectives'. This definition emphasizes uncertainty and the potential impact on project objectives. The effect can be positive (an opportunity) or negative (a threat). This definition is fundamental to the PRINCE2 risk management approach, which addresses both threats and opportunities throughout the project lifecycle.
A. A risk is uncertain, not certain. A certain event is a fact or a planned activity. Also, risks can have a positive impact (opportunities), not just a negative one.
B. An event that has already occurred is classified as an issue or a problem, not a risk. Risk management is a proactive process dealing with future uncertainty.
D. Escalation to the Project Board is a potential response to a risk if it breaches tolerance, not part of the definition of what a risk is.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 7. TSO (The Stationery Office). Glossary, p. 411.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 7. TSO (The Stationery Office). Chapter 12, Section 12.1, p. 156.
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?