PROJECT-MANAGEMENT practice question 3 of 15
According to ATA owner-architect agreements, who is responsible for the cost of evaluating significant substitutions proposed by the contractor…
Choose your answer, then check it against the explanation.
According to ATA owner-architect agreements, who is responsible for the cost of evaluating
significant substitutions proposed by the contractor, subcontractors, or suppliers and the cost of
making subsequent revisions to drawings, specifications, and other documentation?
Question 3 of 15
Keep practicing
Take the free PROJECT-MANAGEMENT practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PROJECT-MANAGEMENT practice questions
- Question 1Which of the following best describes a construction manager (CM) at risk?
- Question 2During the preparation of the construction documents, it was noted that the survey inaccu…
- Question 4During the bidding phase, what is the architect’s role regarding addenda?
- Question 5What is the architect’s role regarding shop drawings?
- Question 6Which four factors will most affect the choice of project delivery method? Check the four…
- Question 7Who is typically responsible for verifying the contractor’s schedule of values?