NCARB certification preparation

PROJECT-MANAGEMENT Practice Questions

Practice exam-style questions, check your answers, and review explanations and source references where they are available.

Exam
PROJECT-MANAGEMENT
Provider
NCARB
Full set
79 questions
Last Update Check
Which of the following best describes a construction manager (CM) at risk?
Answer options
During the preparation of the construction documents, it was noted that the survey inaccurately located the property line. Consequently, the parking layout had to be redesigned to fit within the corrected property boundary. The architect's additional costs and associated delay are the responsibility of which one of the following parties?
Answer options
According to ATA owner-architect agreements, who is responsible for the cost of evaluating significant substitutions proposed by the contractor, subcontractors, or suppliers and the cost of making subsequent revisions to drawings, specifications, and other documentation?
Answer options
During the bidding phase, what is the architect’s role regarding addenda?
Answer options
What is the architect’s role regarding shop drawings?
Answer options
Which four factors will most affect the choice of project delivery method? Check the four that apply.
Answer options
Who is typically responsible for verifying the contractor’s schedule of values?
Answer options
An architecture firm is negotiating a contract with an owner for a $2,000,000 project. The proposed architectural-only fee is 5% of the cost of construction through the end of the Construction Document Phase. During the negotiations, the owner wants to apply for a building permit in 7 weeks without exceeding the original budget constraints. The project staff currently consists of 2 people who have an hourly rate of $100. What is the minimum project staff required to meet the owner's new schedule?
Answer options
A contractor has hired a subcontractor to construct a parking lot for 60 cars. The parking lot will be 60 feet x 270 feet. The subcontractor has quoted a price of $13.25 per square yard to the contractor. If the contractor adds a mark-up of 15%, what is the cost of each parking space?
Answer options
The architect is on site to evaluate the completed work by the contractor. During the evaluation, the architect notices a structural connection that deviates from the contract documents. According to AIA B101, to which party should the architect report this observed deviation?
Answer options
Question 1 of 10

Source context

How this practice set is maintained

Maintained by the CertMage content team, this page loads questions from the exam dataset connected to its preparation resource. When an answer includes a supporting reference, it is shown with that answer so you can review the underlying vendor documentation.

Certification objectives, interfaces, and vendor services can change. Verify important details against the provider's current exam guide and documentation before your exam.

Scroll to Top