Which of the following best describes a construction manager (CM) at risk?
Question 1 discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
During the preparation of the construction documents, it was noted that the survey inaccurately
located the property line. Consequently, the parking layout had to be redesigned to fit within the
corrected property boundary.
The architect's additional costs and associated delay are the responsibility of which one of the
following parties?
Question 2 discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
According to ATA owner-architect agreements, who is responsible for the cost of evaluating
significant substitutions proposed by the contractor, subcontractors, or suppliers and the cost of
making subsequent revisions to drawings, specifications, and other documentation?
Question 3 discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
During the bidding phase, what is the architect’s role regarding addenda?
Question 4 discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
What is the architect’s role regarding shop drawings?
Question 5 discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Which four factors will most affect the choice of project delivery method? Check the four that apply.
Question 6 discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Who is typically responsible for verifying the contractor’s schedule of values?
Question 7 discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
An architecture firm is negotiating a contract with an owner for a $2,000,000 project. The proposed
architectural-only fee is 5% of the cost of construction through the end of the Construction
Document Phase. During the negotiations, the owner wants to apply for a building permit in 7 weeks
without exceeding the original budget constraints. The project staff currently consists of 2 people
who have an hourly rate of $100.
What is the minimum project staff required to meet the owner's new schedule?
Question 8 discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
A contractor has hired a subcontractor to construct a parking lot for 60 cars. The parking lot will be 60
feet x 270 feet. The subcontractor has quoted a price of $13.25 per square yard to the contractor.
If the contractor adds a mark-up of 15%, what is the cost of each parking space?
Question 9 discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
The architect is on site to evaluate the completed work by the contractor. During the evaluation, the
architect notices a structural connection that deviates from the contract documents.
According to AIA B101, to which party should the architect report this observed deviation?
Question 10 discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Question 1 of 10
Source context
How this practice set is maintained
Maintained by the CertMage content team, this page loads questions from the exam dataset connected to its preparation resource. When an answer includes a supporting reference, it is shown with that answer so you can review the underlying vendor documentation.
Certification objectives, interfaces, and vendor services can change. Verify important details against the provider's current exam guide and documentation before your exam.