NCARB certification preparation

PROJECT-PLANNING-DESIGN Practice Questions

Practice exam-style questions, check your answers, and review explanations and source references where they are available.

Exam
PROJECT-PLANNING-DESIGN
Provider
NCARB
Full set
100 questions
Last Update Check
Heavy steel columns and rigid connections between columns and beams Vertical steel trusses in the external walls Light steel columns and flexible connections between columns and beams Vertical steel trusses in the internal walls Which structural design concept minimizes the cost of steel structure needed to resist wind and earthquake loads in high-rise buildings?
Answer options
An elementary school requires a renovation, selective demolition, and a major addition in order to accommodate a growing student population. An architectural firm has prepared schematic design plans incorporating the school's increased programmatic needs, including an enlarged library, cafeteria, and gymnasium; a secure courtyard; and additional space for administrative offices and classrooms. The main entrance was relocated in order to improve the traffic and pedestrian flow at the beginning and end of the school day, and additional parking was provided to comply with current zoning requirements. The existing single-story masonry building was built in 1950. Two small additions were built later: the north addition will be kept and repurposed, but the south addition will be demolished. The building contains asbestos and lead in roof soffits, floor tiles, pipe insulation, and window paint. All existing mechanical systems need to be replaced; new systems have not been selected. Considerations for the renovation include: • The relocated front entrance must be easily recognizable, highly visible, and secure. • Interior and exterior materials need to be durable and maintainable in order to withstand frequent student abuse, but also economical due to strict budget limitations. • Good indoor air quality and increased energy efficiency are priorities for the selection of mechanical equipment. After completion, the entire school should look uniform, without a distinctive difference between the existing building and new addition. Building information: • Construction Type is II-B. The following resources are available for your reference: • Existing Plans, including site and floor plans • Proposed Plans, including site and floor plans • Cost Analysis • Zoning Ordinance Excerpts, for off-street parking requirements • IBC Excerpts, showing relevant code sections • ADA Standards Excerpts, showing relevant sections from the ADA Standards for Accessible Design The building contains asbestos and lead in roof soffits, floor tiles, pipe insulation, and window paint. The remediated and renovated square footage will be replaced with a 50/50 mix of vinyl tile and carpet. What is the total installed cost for the area of vinyl tile?
Answer options
An architect has just received client approval of the Schematic Design documents for a three-story, outpatient medical clinic. The clinic is located within a mixed-use development governed by a City-approved Planned Development (PD) document. The medical clinic design utilizes standardized departmental layouts and includes outpatient clinics, as well as treatment spaces, administrative spaces and public/lobby spaces. The site needs to accommodate four different vehicular traffic flows: patient traffic, staff traffic, service and delivery traffic, and emergency services traffic. In addition, a pedestrian plaza must connect to the mixed-use development sidewalks. The plaza must provide space for bicycle parking and will serve as the future bus stop. The site design addresses several challenges related to building orientation. The southeast facade, with excellent visibility from the highway, is the location of all service equipment. The building entrance faces northwest, convenient to the parking but not visible from the highway. The client believes future patient volumes will outgrow the clinic. The PD document allows for a planned Phase 2 development on the adjacent vacant site to the southwest. Phase 2 would include a second building (2 story, 80,000 BGSF) and/or a parking deck. Other considerations for the project include: Protected tree requirements are defined in the PD document. Easy pedestrian access must be provided from Sycamore Boulevard. All required parking for the clinic must be accommodated on site. Programmed area includes 109,450 Departmental Gross Square Feet (DGSF) / 130,184 Building Gross Square Feet (BGSF). Exterior material percentages are dictated by the PD document and shall not exceed specific percentages for Primary and Secondary Finishes. All service equipment needs to be screened; see PD document for restrictions. Signage opportunities are important to the client. Acoustical privacy is a concern of the healthcare system. The following resources are available for your reference: Drawings, including a perspective, plans, and exterior elevations Building Program, including client's departmental program and detailed program for Treatment 01 (Infusion) Exterior Material Cost Comparisons Planned Development Document IBC Excerpts, showing relevant code sections ADA Excerpts, showing relevant sections from the ADA Standards for Accessible Design Pink granite is specified as an exterior material for the outpatient medical clinic. The owner directs the architect to propose alternate, less expensive materials to be used in lieu of the pink granite. Which of the following materials should be considered to reduce cost? Check the two that apply.
Answer options
A proposed six-story commercial building will have a basement level with finished floor 20'-0" below grade. The building site is located less than 1 mile from the coastline. A site survey indicates that the average site elevation is 5'-0" above sea level. Based on the site-specific conditions, which four issues should the architect address in the design? Check the four that apply.
Answer options
Refer to the exhibit (multi-use building with apartments, offices, stores, parking). NCARB PROJECT PLANNING DESIGN question The multipurpose building shown is located in a cold-winter, mild-summer climate. Which of the following is the best location for the mechanical equipment floor?
Answer options
A client asks that a lighting system be designed using the initial lamp lumen output. Which of the following effects would this request have on the standard light design?
Answer options
Which of the following is the most effective way to reduce noise in mechanical air delivery systems?
Answer options
Refer to the exhibit. NCARB PROJECT PLANNING DESIGN question Refer to the exhibit (residential floor plan with three outlined elevator core locations A, B, C). During design development, an owner has chosen an elevator that does not fit in the location previously selected for the two-car elevator core. The elevator core should be near the main entrance lobby and centrally located. The minimum program requirements for each residential floor are the following: One bicycle room Five studios Five 1-bed units Eight 2-bed units Three 3-bed units Which outlined location meets the requirements?
Answer options
An architect has just received client approval of the Schematic Design documents for a three-story, outpatient medical clinic. The clinic is located within a mixed-use development governed by a City-approved Planned Development (PD) document. The medical clinic design utilizes standardized departmental layouts and includes outpatient clinics, as well as treatment spaces, administrative spaces and public/lobby spaces. The site needs to accommodate four different vehicular traffic flows: patient traffic, staff traffic, service and delivery traffic, and emergency services traffic. In addition, a pedestrian plaza must connect to the mixed-use development sidewalks. The plaza must provide space for bicycle parking and will serve as the future bus stop. The site design addresses several challenges related to building orientation. The southeast facade, with excellent visibility from the highway, is the location of all service equipment. The building entrance faces northwest, convenient to the parking but not visible from the highway. The client believes future patient volumes will outgrow the clinic. The PD document allows for a planned Phase 2 development on the adjacent vacant site to the southwest. Phase 2 would include a second building (2 story, 80,000 BGSF) and/or a parking deck. Other considerations for the project include: Protected tree requirements are defined in the PD document. Easy pedestrian access must be provided from Sycamore Boulevard. All required parking for the clinic must be accommodated on site. Programmed area includes 109,450 Departmental Gross Square Feet (DGSF) / 130,184 Building Gross Square Feet (BGSF). Exterior material percentages are dictated by the PD document and shall not exceed specific percentages for Primary and Secondary Finishes. All service equipment needs to be screened; see PD document for restrictions. Signage opportunities are important to the client. Acoustical privacy is a concern of the healthcare system. The following resources are available for your reference: Drawings, including a perspective, plans, and exterior elevations Building Program, including client's departmental program and detailed program for Treatment 01 (Infusion) Exterior Material Cost Comparisons Planned Development Document IBC Excerpts, showing relevant code sections ADA Excerpts, showing relevant sections from the ADA Standards for Accessible Design Refer to the exhibit. What is the required wall finish for rooms 1201 through 1206 on the first floor?
Answer options
An architect has just received client approval of the Schematic Design documents for a three-story, outpatient medical clinic. The clinic is located within a mixed-use development governed by a City-approved Planned Development (PD) document. The medical clinic design utilizes standardized departmental layouts and includes outpatient clinics, as well as treatment spaces, administrative spaces and public/lobby spaces. The site needs to accommodate four different vehicular traffic flows: patient traffic, staff traffic, service and delivery traffic, and emergency services traffic. In addition, a pedestrian plaza must connect to the mixed-use development sidewalks. The plaza must provide space for bicycle parking and will serve as the future bus stop. The site design addresses several challenges related to building orientation. The southeast facade, with excellent visibility from the highway, is the location of all service equipment. The building entrance faces northwest, convenient to the parking but not visible from the highway. The client believes future patient volumes will outgrow the clinic. The PD document allows for a planned Phase 2 development on the adjacent vacant site to the southwest. Phase 2 would include a second building (2 story, 80,000 BGSF) and/or a parking deck. Other considerations for the project include: Protected tree requirements are defined in the PD document. Easy pedestrian access must be provided from Sycamore Boulevard. All required parking for the clinic must be accommodated on site. Programmed area includes 109,450 Departmental Gross Square Feet (DGSF) / 130,184 Building Gross Square Feet (BGSF). Exterior material percentages are dictated by the PD document and shall not exceed specific percentages for Primary and Secondary Finishes. All service equipment needs to be screened; see PD document for restrictions. Signage opportunities are important to the client. Acoustical privacy is a concern of the healthcare system. The following resources are available for your reference: Drawings, including a perspective, plans, and exterior elevations Building Program, including client's departmental program and detailed program for Treatment 01 (Infusion) Exterior Material Cost Comparisons Planned Development Document IBC Excerpts, showing relevant code sections ADA Excerpts, showing relevant sections from the ADA Standards for Accessible Design NCARB PROJECT PLANNING DESIGN question NCARB PROJECT PLANNING DESIGN question Which of the following design solutions best addresses the client’s concerns related to building orientation, vehicular circulation, and future expansion?
Answer options
Question 1 of 10

Source context

How this practice set is maintained

Maintained by the CertMage content team, this page loads questions from the exam dataset connected to its preparation resource. When an answer includes a supporting reference, it is shown with that answer so you can review the underlying vendor documentation.

Certification objectives, interfaces, and vendor services can change. Verify important details against the provider's current exam guide and documentation before your exam.

Scroll to Top