PSA-SYSADMIN practice question 7 of 15
You are in the process of setting up your organization's Resources and learn that Resources in France will be working a 35-hour work week. What will you need to do to set them up with the proper work calendar?
Full set: 60 questionsCertinia PSA is designed to accommodate diverse global work schedules by allowing the creation of multiple, distinct work calendars. The correct and most efficient method is to create a specific work calendar that accurately reflects the 35-hour work week for French employees. This calendar can then be associated directly with the relevant resource records. This approach ensures that all system calculations, including resource capacity, availability for scheduling, and utilization metrics, are precise. It also provides the flexibility to add region-specific holidays, ensuring accurate project planning and resource management for that specific group.
A. This is incorrect because the premise that PSA only allows one work calendar is false. The platform is designed to support multiple calendars for different regions or working arrangements.
B. This is incorrect because it introduces data inaccuracies. The work calendar is a foundational element for capacity, scheduling, and forecasting, not just a variable for manual utilization calculations.
1. Certinia PSA Administration Guide: The section on "Work Calendars" explicitly details the process for creating and managing multiple calendars. It states, "You can create multiple work calendars to reflect the different working patterns of your resources." The guide further explains how to set the hours per workday and associate the calendar with specific resources, regions, practices, or groups. (Refer to the "Setting Up Work Calendars" and "Associating Work Calendars" sections in the official documentation).
2. Certinia PSA Resource Management Documentation: This documentation outlines that the Work Calendar field on the Resource object is a lookup to the Work Calendar object. This object relationship is fundamental to the system's design, allowing each resource to be assigned a specific calendar that dictates their capacity and availability, directly supporting the methodology described in the correct answer. (Refer to the "Resource Object Fields" section).
Keep practicing
Take the free PSA-SYSADMIN practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSA-SYSADMIN practice questions
- Question 1Your organization has decided to change the default scheduling strategy to be used as a s…
- Question 2A Resource Record is required to perform which two of the following actions? (Choose two.)
- Question 3A Services manager has asked you to set up a unique "FF Navigation" lightning component o…
- Question 4Actuals are the result of calculations run on transactions that occur in a business recor…
- Question 5A Sales Associate is unable to enter a Resource Request. They have a Resource Contact rec…
- Question 6A user has reported they cannot see their projects when viewing the Project Management Wo…