PSM-1 practice question 14 of 35
A Scrum Team is only allowed to meet with stakeholders during Sprint Review.
Full set: 298 questionsThe statement is false. While the Sprint Review is a key formal event for the Scrum Team and stakeholders to collaborate, it is not the only time they are allowed to interact. The Scrum framework encourages ongoing communication and collaboration throughout the Sprint. The Product Owner is responsible for representing the needs of stakeholders and frequently communicates with them to refine the Product Backlog. Furthermore, Developers may need to collaborate with stakeholders to clarify requirements to ensure the Increment meets their needs and expectations. Restricting this vital communication to a single event would impede the empirical process of transparency, inspection, and adaptation that is central to Scrum.
The "True" option is incorrect because it presents a rigid anti-pattern. Limiting stakeholder interaction solely to the Sprint Review would create a significant delay in feedback, increase the risk of building the wrong product, and undermine the collaborative spirit of Scrum. The framework is designed to be adaptive, and frequent communication is essential for that adaptiveness.
1. Schwaber
K.
& Sutherland
J. (2020). The Scrum Guide. Scrum.org.
Section: Scrum Team > Product Owner: "The Product Owner is one person
not a committee. The Product Owner may represent the needs of many stakeholders in the Product Backlog... For Product Owners to succeed
the entire organization must respect their decisions." This role inherently requires continuous communication with stakeholders to understand and represent their needs effectively
which cannot be confined to a single meeting per Sprint.
Section: Scrum Events > The Sprint Review: "The purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future adaptations. The Scrum Team presents the results of their work to key stakeholders and progress toward the Product Goal is discussed." This describes the Sprint Review as a formal event for inspection and adaptation with stakeholders
but it does not prescribe it as the only point of interaction.
Section: Scrum Theory: "Scrum is founded on empiricism and lean thinking. Empiricism asserts that knowledge comes from experience and making decisions based on what is observed." Limiting stakeholder interaction would severely limit the opportunities for observation and experience
thus hindering the empirical process.
Keep practicing
Take the free PSM-1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSM-1 practice questions
- Question 1What is the role of management in Scrum?
- Question 2What are two effective ways for the Scrum Team to make non-functional requirements visibl…
- Question 3When is the Sprint Backlog created?
- Question 4When might a Sprint be abnormally cancelled?
- Question 5What is the tactic a Scrum Master should use to divide a group of 100 people into multipl…
- Question 6Which two of the following are appropriate topics for discussion during a Sprint Retrospe…