Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces).
Full set: 298 questionsThe statement is false. A core principle of Scrum is that teams are cross-functional, meaning they possess all the necessary skills within the team to create a valuable, done Increment. This requires the ability to work across all technical layers (e.g., user interface, business logic, database, testing) to deliver a complete, vertical slice of functionality. The structure described in the question—a team optimized for a single technical layer—is known as a "component team." This structure is generally considered an anti-pattern in Scrum because it creates dependencies between teams, hinders the flow of work, and makes it difficult to produce a fully integrated and potentially releasable Increment each Sprint.
The option "True" is incorrect because it fundamentally misrepresents the definition and purpose of a cross-functional team as defined in the Scrum framework. It describes a siloed, component-based team structure, which is the opposite of the integrated, end-to-end capability that a cross-functional Scrum Team is designed to have.
1. Schwaber
K.
& Sutherland
J. (2020). The 2020 Scrum Guide.
Page 5
"Scrum Team": "Scrum Teams are cross-functional
meaning the members have all the skills necessary to create value each Sprint." This directly refutes the idea that they are limited to a single layer; creating "value" in the form of a working Increment typically requires touching multiple layers of an application.
Page 6
"Developers": "The Developers are the people in the Scrum Team that are committed to creating any aspect of a usable Increment each Sprint." This implies a collective ownership and capability to work on whatever is necessary to complete the Increment
not just a single
pre-defined technical component.
2. Moe
N. B.
Dingsøyr
T.
& Dybå
T. (2010). A teamwork model for understanding an agile team: A case study of a Scrum project. Information and Software Technology
52(5)
480-491.
Section 3.1
"Team characteristics": The paper emphasizes that in Scrum
"The team should be cross-functional and have all the competencies needed to accomplish the project without depending on people outside the team." This autonomy is achieved by having skills that span the entire software development lifecycle and technical stack
not by specializing in a single layer which would create external dependencies.
DOI: https://doi.org/10.1016/j.infsof.2009.11.004
3. Rigby
D. K.
Sutherland
J.
& Takeuchi
H. (2016). Embracing Agile. Harvard Business Review
94(5)
40-50.
Page 43
"How to Implement Agile": The article states
"The basic unit of agile is a small
self-governing
cross-functional team." It further explains that these teams have "end-to-end accountability for their work
" which is impossible if a team is restricted to only one technical layer of a system.
Keep practicing
Take the free PSM-1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSM-1 practice questions
- Question 1What is the role of management in Scrum?
- Question 2What are two effective ways for the Scrum Team to make non-functional requirements visibl…
- Question 3When is the Sprint Backlog created?
- Question 4When might a Sprint be abnormally cancelled?
- Question 5What is the tactic a Scrum Master should use to divide a group of 100 people into multipl…
- Question 6Which two of the following are appropriate topics for discussion during a Sprint Retrospe…