PSM-1 practice question 24 of 35

True or False: An increment must be released to customers or users at the end of each sprint.

Full set: 298 questions
Answer options
A: True
B: False
Correct Answer:
FALSE
Explanation

The Scrum Guide requires that each Sprint produces a "Done," usable Increment that meets the Scrum Team’s Definition of Done. However, it does not mandate that this Increment must be released to customers or users at the end of every Sprint. The decision to release value is a business decision made by the Product Owner. The Scrum framework intentionally decouples the development cadence (the Sprint) from the release cadence, providing flexibility. An Increment is considered potentially releasable, but the actual release can occur whenever it provides the most value to stakeholders—which could be during a Sprint, at the end of a Sprint, or after several Sprints have been completed.

Why Incorrect

The statement "True" is incorrect because it presents the release of an Increment as a mandatory, required event at the end of every Sprint. This contradicts a core principle of Scrum, which is to provide the Product Owner with the flexibility to release value when it makes the most sense for the product and its users. The requirement is to create a usable and potentially releasable Increment, not to release it on a fixed schedule tied to the Sprint's conclusion.

References

1. Schwaber

K.

& Sutherland

J. (2020). The Scrum Guide. Scrum.org.

Reference Point: Section "Scrum Artifacts

" subsection "Increment

" Page 11.

Explanation from Source: The guide explicitly states

"an Increment may be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value." This sentence directly confirms that a release is not a mandatory event at the end of a Sprint and can happen at any time. The focus is on the creation of a usable Increment

which gives the Product Owner the option

but not the obligation

to release it.