PSM-1 practice question 24 of 35
True or False: An increment must be released to customers or users at the end of each sprint.
Full set: 298 questionsThe Scrum Guide requires that each Sprint produces a "Done," usable Increment that meets the Scrum Team’s Definition of Done. However, it does not mandate that this Increment must be released to customers or users at the end of every Sprint. The decision to release value is a business decision made by the Product Owner. The Scrum framework intentionally decouples the development cadence (the Sprint) from the release cadence, providing flexibility. An Increment is considered potentially releasable, but the actual release can occur whenever it provides the most value to stakeholders—which could be during a Sprint, at the end of a Sprint, or after several Sprints have been completed.
The statement "True" is incorrect because it presents the release of an Increment as a mandatory, required event at the end of every Sprint. This contradicts a core principle of Scrum, which is to provide the Product Owner with the flexibility to release value when it makes the most sense for the product and its users. The requirement is to create a usable and potentially releasable Increment, not to release it on a fixed schedule tied to the Sprint's conclusion.
1. Schwaber
K.
& Sutherland
J. (2020). The Scrum Guide. Scrum.org.
Reference Point: Section "Scrum Artifacts
" subsection "Increment
" Page 11.
Explanation from Source: The guide explicitly states
"an Increment may be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value." This sentence directly confirms that a release is not a mandatory event at the end of a Sprint and can happen at any time. The focus is on the creation of a usable Increment
which gives the Product Owner the option
but not the obligation
to release it.
Keep practicing
Take the free PSM-1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSM-1 practice questions
- Question 1What is the role of management in Scrum?
- Question 2What are two effective ways for the Scrum Team to make non-functional requirements visibl…
- Question 3When is the Sprint Backlog created?
- Question 4When might a Sprint be abnormally cancelled?
- Question 5What is the tactic a Scrum Master should use to divide a group of 100 people into multipl…
- Question 6Which two of the following are appropriate topics for discussion during a Sprint Retrospe…