PSM-2 practice question 3 of 15

A Scrum Team selected a Product Backlog item during Sprint Planning. However, at the end of the Sprint the work does not meet the Definition of Done…

Choose your answer, then check it against the explanation.

A Scrum Team selected a Product Backlog item during Sprint Planning. However, at the end of the Sprint the work does not meet the Definition of Done. What two things should happen with this incomplete Product Backlog item? (choose the best two answers)
Answer options
Question 3 of 15

Keep practicing

Take the free PSM-2 practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PSM-2 practice questions

Scroll to Top