When should the Product Owner update the project plan? (choose the best answer)
Full set: 178 questionsDomain Agile Product Management
Scrum does not use a traditional, static project plan. Instead, the Product Backlog serves as the single, authoritative plan for the product. It is an emergent and dynamic artifact that evolves throughout the product's lifecycle. The Product Owner is responsible for managing this backlog, which involves continuously updating and re-ordering it as new information, market feedback, and stakeholder insights become available. This ensures the plan always reflects the most current understanding of what is needed to maximize the product's value.
A. The Product Owner prepares the Product Backlog for Sprint Planning, but the Developers determine how much work they can take on; the PO does not dictate a plan for the Sprint's volume.
C. The Daily Scrum is a planning event for the Developers to inspect progress toward the Sprint Goal. It is not a designated time for the Product Owner to update the overall product plan.
D. The Sprint Retrospective is focused on inspecting the Scrum Team's process and effectiveness, not on updating the Product Backlog or product plan.
1. Schwaber
K.
& Sutherland
J. (2020). The Scrum Guide. Scrum.org.
Page 11
"Product Backlog" section: "The Product Backlog is an emergent
ordered list of what is needed to improve the product. It is the single source of work undertaken by the Scrum Team." This establishes the Product Backlog as the plan.
Page 12
"Product Backlog" section: "The Product Backlog is a living artifact... Product Backlog refinement is the act of breaking down and further defining Product Backlog items into smaller more precise items. This is an ongoing activity to add details
such as a description
order
and size." This confirms its continuous
emergent nature.
2. Hohl
P.
Klünder
J.
van Bennekum
A.
et al. (2018). Backlog Refinement in Large-Scale Agile System Development. In: Product-Focused Software Process Improvement. PROFES 2018. Lecture Notes in Computer Science
vol 11271. Springer
Cham.
Page 1
Abstract: "The product backlog is the central planning artifact in Scrum..." This academic source confirms the role of the Product Backlog as the primary plan in the Scrum framework. (DOI: https://doi.org/10.1007/978-3-030-03673-723)
Keep practicing
Take the free PSPO-I practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSPO-I practice questions
- Question 1How often should customer satisfaction be measured? (choose the best answer)
- Question 2True or False: The Scrum Team is accountable for creating a valuable increment every Spri…
- Question 3One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily S…
- Question 4Which outcome is expected as a Scrum Team matures? (choose the best answer)
- Question 5Who must attend the Daily Scrum? (choose the best answer)
- Question 6During a Sprint, when is new work or further decomposition of work added to the Sprint Ba…