PSPO-I practice question 21 of 25
Which of the following are appropriate topics for discussion during a Sprint Retrospective? (choose the best two answers)
Full set: 178 questionsDomain Scrum Framework
The Sprint Retrospective is a formal event for the Scrum Team to inspect itself and create a plan for improvements. Its purpose is to improve quality and effectiveness by examining the past Sprint regarding individuals, interactions, processes, and tools. Therefore, discussing how the team collaborates (C) and identifying high-priority process improvements for the next Sprint (A) are core activities of this event. The most impactful improvements are often added to the next Sprint Backlog to ensure they are acted upon.
B. The order of items in the Product Backlog. This is the accountability of the Product Owner and is typically addressed during Product Backlog refinement activities, not the process-focused Sprint Retrospective.
D. Documenting acceptance criteria for items in the next Sprint. This is a product-focused activity related to Product Backlog refinement or Sprint Planning, defining the "what" of the work, not inspecting the team's process. ---
1. Schwaber
K.
& Sutherland
J. (2020). The Scrum Guide. Scrum.org.
Page 10
"Sprint Retrospective" section: "The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness."
Page 10
"Sprint Retrospective" section: "The Scrum Team inspects how the last Sprint went with regards to individuals
interactions
processes
tools
and their Definition of Done." (Supports C)
Page 11
"Sprint Retrospective" section: "The Scrum Team identifies the most helpful changes to improve its effectiveness. The most impactful improvements are addressed as soon as possible and may even be added to the Sprint Backlog for the next Sprint." (Supports A)
2. Verheyen
G. (2021). Scrum – A Pocket Guide (3rd edition). Van Haren Publishing.
Chapter 5
"The Sprint Retrospective": This chapter emphasizes that the Retrospective is a "formal opportunity for the Scrum Team to inspect and adapt its way of working
" distinct from product-related discussions. This supports the exclusion of options B and D.
Keep practicing
Take the free PSPO-I practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSPO-I practice questions
- Question 1How often should customer satisfaction be measured? (choose the best answer)
- Question 2True or False: The Scrum Team is accountable for creating a valuable increment every Spri…
- Question 3One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily S…
- Question 4Which outcome is expected as a Scrum Team matures? (choose the best answer)
- Question 5Who must attend the Daily Scrum? (choose the best answer)
- Question 6During a Sprint, when is new work or further decomposition of work added to the Sprint Ba…