SAFE-AGILIST practice question 7 of 15

Who decides the Team PI Objective Business Value scoring after negotiation?

Full set: 87 questions
Answer options
A: Product Management
B: Business Owner
C: The Agile Team
D: The RTE
Correct Answer:
[B]
Explanation

During PI Planning, after Agile Teams present their draft plans and PI objectives, the Business Owners circulate and assign a business value (on a scale of 1-10) to each objective. This is a collaborative process involving negotiation and conversation with the team, but the final decision on the value score rests with the Business Owners. They have the ultimate responsibility for ensuring that the team's plans align with business and customer needs, and this scoring is a key mechanism for that alignment.

Why Incorrect

A. Product Management: Product Management is responsible for prioritizing the ART backlog (Features), but Business Owners quantify the value of the team's PI objectives.
C. The Agile Team: The Agile Team writes the PI objectives and commits to them, but they do not assign the external business value; they receive this feedback from the Business Owners.
D. The RTE: The Release Train Engineer (RTE) facilitates the PI Planning event and serves the ART, but they do not have the authority to assign business value.

References

- Scaled Agile, Inc. (2023). Business Owners. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/business-owners/. See the "Responsibilities" section, which states, "During PI planning, they are involved in mission setting, planning, and assigning business value to PI Objectives."

- Scaled Agile, Inc. (2023). PI Objectives. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/pi-objectives/. See the section "Assigning Business Value," which details the role of Business Owners in this activity.

Scroll to Top