SAFE-SGP practice question 6 of 10
When do organizations begin realizing better results when following the Implementation Roadmap?
Full set: 45 questionsAccording to the Implementation Roadmap article on the Scaled Agile Framework website, organizations begin realizing better results when following the Implementation Roadmap as soon as the first Program Increment (PI). The article states that “The first PI is a critical milestone. It’s the first time the new ART delivers a fully integrated and tested increment of value. It’s also the first time the ART demonstrates its new way of working to the enterprise and its stakeholders. The first PI is a big deal. It’s a celebration of the new culture and the new way of working. It’s also the first time the enterprise can see the benefits of the new approach.” Therefore, the correct answer is B, as soon as the first Program Increment. The other options are not accurate, as the roadmap consists of more than just steps, training, or metrics. It is a continuous journey of learning and improvement.
Keep practicing
Take the free SAFE-SGP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SAFE-SGP practice questions
- Question 1Which represents a good example of an agency Strategic Theme?
- Question 2What is one benefit of Program Increment (PI) Planning?
- Question 3How can Lean-Agile leaders exemplify the SAFe Core Value of alignment?
- Question 4At what levels are confidence votes taken once dependencies and program risks are address…
- Question 5Which aspect of leading by example challenges Lean-Agile leaders to 'walk the talk' by be…
- Question 7Which two statements accurately describe the SAFe Implementation Roadmap? (Choose two.)