Which architecture deliverable identifies the organization's tolerance to security issues and how the organization plans to react if a security issue occurs?

Full set: 118 questions

Domain Secure Software Architectures and Technologies

Answer options
A: Threat Modeling Artifacts
B: Risk Mitigation Plan Correct answer
C: Business Requirements
D: Policy Compliance Analysis
Correct Answer:
B. Risk Mitigation Plan
Explanation

A Risk Mitigation Plan is the specific architecture deliverable that documents an organization's strategy for managing identified security risks. This plan is created after a risk assessment and is directly informed by the organization's risk tolerance—the level of risk it is willing to accept. The plan outlines specific controls and actions to reduce risks to an acceptable level. Crucially, it also includes contingency and incident response strategies, which define precisely how the organization will react if a security issue or incident occurs, thereby addressing both parts of the question.

Why Incorrect

A. Threat Modeling Artifacts: These documents identify and analyze potential threats and vulnerabilities but do not define the organization's risk tolerance or its official response plans.
C. Business Requirements: These define the high-level goals and needs for the system, which inform security policies and risk tolerance, but they are not the plan for mitigation or reaction.
D. Policy Compliance Analysis: This is a verification artifact that assesses whether the system design adheres to established policies; it does not create the risk response strategy itself. ---

References

1. NIST Special Publication 800-37, Revision 2, "Risk Management Framework for Information Systems and Organizations."

Section 2.5, "Step 4: Implement," discusses how organizations implement the risk responses identified in the risk response plan. It states, "The risk response strategy is the course of action to be taken regarding the risk... Risk response options include acceptance, avoidance, mitigation, sharing, or transferring the risk." The mitigation plan documents these choices.

Appendix F, "Risk Mitigation Plan," describes the plan's purpose as documenting the "planned implementation of controls" and the "course of action to address the vulnerabilities in the system." This includes reactive measures.

2. Carnegie Mellon University, Software Engineering Institute (SEI), "The CERT® Resilience Management Model (CERT-RMM) v1.2."

Process Area: Risk Management (RISK), Specific Goal 3 (SG 3), "Handle risks." This section details the need to "Develop a risk mitigation plan for risks that are not accepted." This explicitly links the concept of risk acceptance (tolerance) to the creation of a mitigation plan that includes response actions.

3. Ross, R., McEvilley, M., & Oren, J. C. (2016). "Systems Security Engineering: Considerations for a Multidisciplinary Approach in the Engineering of Trustworthy Secure Systems" (NIST Special Publication 800-160, Vol. 1).

Section 3.3.4.4, "Risk Response," states that a key part of the risk management process is to "develop a risk response strategy" and that "The risk response is implemented through a risk mitigation plan." This confirms the plan is the deliverable containing the response strategy based on tolerance.