According to SAFe, a Feature should be sized to fit into what duration?
Full set: 269 questionsIn SAFe, a Feature is a unit of work that delivers business value and fulfills a stakeholder need. A key characteristic of a Feature is its size. To ensure a continuous flow of value and enable effective planning and execution for an Agile Release Train (ART), Features are defined and sized to be completed within a single Program Increment (PI). If a business need is too large to fit into one PI, it is typically defined as an Epic and broken down into smaller Features.
A. One month is not a standard SAFe timebox for sizing Features; it is shorter than a typical PI.
B. One year is far too long for a Feature; work of this magnitude would be classified as a Portfolio Epic.
C. One Iteration is the timebox for a Story, which is a smaller component of a Feature.
1. Scaled Agile, Inc. (2023). Feature. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/features-and-capabilities/. (See the introductory paragraph, which states, "Features are sized to fit in a Program Increment (PI).").
Keep practicing
Take the free SP-SAFE-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SP-SAFE-PRACTITIONER practice questions
- Question 1During which PI Planning activity do Business Owners assign business value to PI Objectiv…
- Question 2What is an example of an ART event?
- Question 3What is used to capture the current state of the Portfolio and provide input for defining…
- Question 5Why do Lean-Agile leaders try to connect the silos of business, software, test, and quali…
- Question 6What else does the SAFe principle, "unlock the intrinsic motivation of knowledge workers"…
- Question 7Which factor helps unlock the intrinsic motivation of knowledge workers?