SP-SAFE-PRACTITIONER practice question 27 of 35
What is the purpose of the Team Sync?
Full set: 269 questionsThe Team Sync is the SAFe event for Agile Teams to inspect their progress toward the Iteration Goal and coordinate their activities for the next 24 hours. It is analogous to the Daily Stand-up meeting in Scrum. The primary purpose is to ensure the team members are aligned on their daily work, discuss any impediments, and adjust their plan to meet the iteration commitments. This frequent synchronization is crucial for maintaining flow and adapting to challenges within the Iteration.
A. ART PI risks are identified and managed at the Program Level, typically during PI Planning and the ART Sync, not the daily Team Sync.
C. Iteration goals are defined and agreed upon during Iteration Planning, which occurs at the beginning of each iteration.
D. Announcements for the entire Agile Release Train (ART) are made at ART-level events like the ART Sync, not at individual team meetings.
1. Scaled Agile, Inc. (2023). Team Sync. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/team-sync/. (Section: "Details," Paragraph 1).
2. Scaled Agile, Inc. (2023). Agile Teams. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/agile-teams/. (Section: "Team Events," bullet point on Team Sync).
Keep practicing
Take the free SP-SAFE-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SP-SAFE-PRACTITIONER practice questions
- Question 1During which PI Planning activity do Business Owners assign business value to PI Objectiv…
- Question 2What is an example of an ART event?
- Question 3What is used to capture the current state of the Portfolio and provide input for defining…
- Question 4According to SAFe, a Feature should be sized to fit into what duration?
- Question 5Why do Lean-Agile leaders try to connect the silos of business, software, test, and quali…
- Question 6What else does the SAFe principle, "unlock the intrinsic motivation of knowledge workers"…