SP-SAFE-PRACTITIONER practice question 21 of 35
What visibility should Scrum Masters provide during the Agile Release Train Sync?
Full set: 269 questionsThe Agile Release Train (ART) Sync event is held to coordinate progress. It typically consists of a 'Coach Sync' and a 'PO Sync'. The Coach Sync is the specific forum where Scrum Masters, the Release Train Engineer (RTE), and other facilitators meet. During this meeting, their primary function is to provide visibility into the progress of their teams' objectives, discuss dependencies, and raise any impediments that are blocking progress or threatening the ART's ability to meet its PI Objectives. This ensures that problems are managed and resolved at the ART level in a timely manner.
B. Visibility into system Solution Intent is primarily the responsibility of Product Management and System Architects, not Scrum Masters during an ART sync.
C. "Collaboration deployment" is not a standard SAFe term. While deployment is discussed, this option is too vague and imprecise compared to progress and impediments.
D. Single source design decisions are an architectural concern, typically handled by System Architects and not a primary reporting topic for Scrum Masters.
- Scaled Agile, Inc. (2023). ART Sync. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/art-sync/. The article states, "The coach sync provides visibility into progress and impediments."
- Scaled Agile, Inc. (2023). Scrum Master/Team Coach. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/scrum-master/. The responsibilities section includes facilitating team events and assisting the team in communicating with other teams, which is done at the ART Sync.
Keep practicing
Take the free SP-SAFE-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SP-SAFE-PRACTITIONER practice questions
- Question 1During which PI Planning activity do Business Owners assign business value to PI Objectiv…
- Question 2What is an example of an ART event?
- Question 3What is used to capture the current state of the Portfolio and provide input for defining…
- Question 4According to SAFe, a Feature should be sized to fit into what duration?
- Question 5Why do Lean-Agile leaders try to connect the silos of business, software, test, and quali…
- Question 6What else does the SAFe principle, "unlock the intrinsic motivation of knowledge workers"…