1Z0-1057-26 practice question 22 of 25
Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the…
Full set: 126 questionsIf a transaction matches exactly one level of the resource breakdown structure, the system posts the entire cost to that single level. When several branches are possible and their summed precedence values tie, the branch whose lowest-level element has the smallest precedence number wins the mapping. These two rules are explicitly stated in the resource-mapping precedence algorithm.
A. User-defined resource types do not override the numeric precedence algorithm.
B. The branch with the LOWEST, not highest, summed precedence is selected.
1. Oracle Fusion Cloud Project Management: Implementing Project Financial Management (24A), sec. “Define Resource Breakdown Structures”, topic “Resource Mapping Precedence Rules”, pp. 238-239.
2. Oracle Fusion Cloud Project Management: Defining and Managing Financial Projects (23D), Appendix B “Precedence Numbers”, p. B-3.
Keep practicing
Take the free 1Z0-1057-26 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1057-26 practice questions
- Question 1While creating a new project template, you notice that a default Asset Cost Allocation me…
- Question 2Your customer wants to calculate Estimate to Complete (ETC) as the difference between Cur…
- Question 3Which step within the functional setup manager helps you to move your verified setup data…
- Question 4Which three Cost Collection Flexfield core attributes can be derived during import if not…
- Question 5You have been asked to set up one active person, who is not a team member in the project,…
- Question 6Your customer wants a team member who is assigned to a project to be able to create and s…