1Z0-511 practice question 9 of 15
Which two options are not task attributes for financial task structure?
Full set: 70 questionsIncorrect: Not A: Task types assign default attributes to tasks and control how Oracle Projects processes tasks. Task types specify basic task attributes. Not C: Work types represent a classification of work. You use work types to classify both actual and scheduled work. Not E: Oracle Projects uses start and finish dates to control processing, indicate estimated and scheduled duration, and serve as tools to evaluate project performance. The start and finish dates at the project level are: Actual: Actual dates when work on the project started and finished. You can use these dates to drive future timecard and earned value functionality. (not E) Scheduled: Scheduled start and finish dates for the project. Target: The expected lifespan of the project. Estimated: A task manager's estimate of when work on the project will be started and finished. Baseline: The baselined schedule
Keep practicing
Take the free 1Z0-511 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-511 practice questions
- Question 1You are setting up an AutoAccounting rule and trying to use "Class Code" as the parameter…
- Question 2Which statement is true about the use of the calendar assigned to a project?
- Question 4A project has been mistakenly set up as a capital project, instead of a contract project.…
- Question 5Which project class type can include revenue budgets?
- Question 6A company has multi-currency projects and tasks. What is the hierarchy in which the curre…
- Question 7A customer is billed using deliverable billing events, which are currently approved by th…