1Z0-511 practice question 10 of 15

You have defined a Non-Labor resource "Mini Truck" with an expenditure type "Vehicle" that has a rate of $100. This resource is attached to three Non-Labor resource organizations: "Construction- East," "Construction-West," and "Construction-Central." How do you set up a rate of $150 for usage charges when the "Mini Truck" owned by "Construction- Central" is charged to a project?

Full set: 70 questions
Answer options
A: In the Project setup, enter a rate of $150 for "Construction-Central" in the organization overrides.
B: In the Non-Labor resources setup, select the "Construction-Central" organization and enter a rate of $150.
C: Create a new rate schedule with a rate of $150 for "Mini Truck" and attach it to the project.
D: Create a new rate schedule with a rate of $150 for "Mini Truck" and attach it to "Construction- Central." Correct answer
E: Write custom code in Non-Labor cost override extension.
Correct Answer:
D. Create a new rate schedule with a rate of $150 for "Mini Truck" and attach it to "Construction- Central."