AD0-E903 practice question 5 of 15
A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it. What impact does this have on the project progress status?
Full set: 70 questionsIn Adobe Workfront, the project's "Condition" is an automatic health indicator based on the progress of its tasks, particularly those on the critical path. A critical path task is one that directly impacts the project's finish date. Although the task is not yet overdue, the lack of progress by the fourth day of a five-day window represents a significant risk to the project timeline. Workfront's system is designed to proactively flag such risks. This scenario is a classic trigger for the system to automatically change the project's condition to "At Risk," alerting the project manager to a potential delay before it becomes critical.
A. The next team member cannot start his task. This describes a potential consequence of the delay (a successor dependency), not the project's overall progress status indicator within Workfront, which is what the question asks for.
B. No impact as the task is not overdue. This is incorrect. Tasks on the critical path have zero float, meaning any delay in their completion directly delays the entire project. The lack of progress is a significant risk and has an immediate impact on the project's health status.
1. Adobe Workfront Documentation, "Overview of the project Condition": This document explicitly states, "The Condition of a project is determined by the progress status of the tasks on the critical path." It defines "At Risk" as the condition when the project is in danger of not meeting its Planned Completion Date. The scenario described directly endangers the timeline. (Adobe Experience League, Workfront for Project Managers section).
2. Adobe Workfront Documentation, "Track progress on the critical path": This guide explains that Workfront highlights tasks on the critical path because their timeliness is essential for on-time project completion. A lack of progress on such a task, as described in the question, would cause the project's Projected Completion Date to slip, triggering a change in the project's Condition. (Adobe Experience League, Workfront for Project Managers section).
3. Adobe Workfront Documentation, "Configure system-wide project preferences": This documentation details how system administrators can define the automatic triggers for condition changes. Default settings typically flag projects as "At Risk" based on deviations between the Planned and Projected Completion Dates, which are directly affected by delays on the critical path. (Adobe Experience League, Workfront for Administrators section).
Keep practicing
Take the free AD0-E903 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AD0-E903 practice questions
- Question 1Which two options are available with Workfront reports? (Choose two.)
- Question 2A marketing team determines that in the future, their projects must be reviewed by the Pr…
- Question 3Which project Condition is set when the Progress Status of the project is Behind or At Ri…
- Question 4What are two ways to associate milestone steps to tasks? (Choose two.)
- Question 6How would a project manager create a custom Workfront report to show information about is…
- Question 7An executive wants to see the actual cost of projects within a selected portfolio, allowi…