AD0-E903 practice question 3 of 15
Which project Condition is set when the Progress Status of the project is Behind or At Risk?
Full set: 70 questionsIn Adobe Workfront, the project's 'Condition' reflects its overall health, while the 'Progress Status' measures its timeliness against the planned completion date. Workfront can be configured to automatically update the Condition based on the Progress Status. When a project's Progress Status becomes 'At Risk' (projected to finish after the planned date) or 'Behind' (projected to finish significantly after the planned date), the system automatically sets the project's Condition to 'At Risk'. This serves as an early warning indicator to stakeholders that the project requires attention to prevent further delays.
A. Late: "Late" is a value for the 'Progress Status' field, indicating the project's planned completion date has passed, not a value for the 'Condition' field.
C. In Trouble: The "In Trouble" condition typically represents a more severe state of project health and is usually set manually by a project manager rather than being the default automatic condition for a 'Behind' or 'At Risk' status.
1. Adobe Experience League. (2024). Update the Condition for a project. Adobe Workfront Documentation. Retrieved from https://experienceleague.adobe.com/docs/workfront/using/projects/manage-projects/update-project-condition.html.
Reference Point: The section "How Workfront sets the project Condition automatically" states
"Workfront can automatically set the Condition of a project to At Risk when its Progress Status becomes At Risk or Behind."
2. Adobe Experience League. (2024). Overview of Project Progress Status. Adobe Workfront Documentation. Retrieved from https://experienceleague.adobe.com/docs/workfront/using/projects/manage-projects/project-progress-status.html.
Reference Point: This document defines the different Progress Statuses
including 'At Risk'
'Behind'
and 'Late'
distinguishing them from the project 'Condition'.
3. Adobe Experience League. (2024). Overview of Project Condition and Condition Type. Adobe Workfront Documentation. Retrieved from https://experienceleague.adobe.com/docs/workfront/using/projects/manage-projects/project-condition-and-condition-type.html.
Reference Point: This document defines the default project Conditions as 'On Target'
'At Risk'
and 'In Trouble'
clarifying the purpose of each.
Keep practicing
Take the free AD0-E903 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AD0-E903 practice questions
- Question 1Which two options are available with Workfront reports? (Choose two.)
- Question 2A marketing team determines that in the future, their projects must be reviewed by the Pr…
- Question 4What are two ways to associate milestone steps to tasks? (Choose two.)
- Question 5A team member has five days to complete a critical path task, and the task requires only …
- Question 6How would a project manager create a custom Workfront report to show information about is…
- Question 7An executive wants to see the actual cost of projects within a selected portfolio, allowi…