AD0-E911 practice question 3 of 10
What is unique to a Scrum iteration?
Full set: 95 questionsThe Burndown Chart is a graphical representation of work remaining versus time, which is a hallmark artifact for tracking progress within a time-boxed Scrum iteration (or Sprint). Within Adobe Workfront's agile tools, the Burndown Chart is a specific feature of the iteration view, designed to help Scrum teams visualize their progress toward completing the work committed in the Sprint Backlog. It provides immediate insight into whether the team is on track to meet the sprint goal.
A. Backlog of stories and issues: A backlog is a core component of many agile methodologies, including Kanban, not just Scrum. Therefore, it is not unique to a Scrum iteration.
B. Workload Balancer for assigning users to tasks: The Workload Balancer is a general resource management tool within Adobe Workfront used for capacity planning across all types of projects, not exclusively for Scrum iterations.
1. Adobe Workfront Documentation, "Burndown chart overview": This document explicitly defines the tool's purpose: "The burndown chart is a graphical representation of the work remaining in an iteration versus the time. You can use the burndown chart to determine whether your team is on track to complete the work of the iteration in the time allotted." This directly links the Burndown Chart to the Scrum iteration concept.
2. Adobe Workfront Documentation, "Create a backlog": This source clarifies that backlogs are not exclusive to Scrum. It states, "You can manage the backlog of a Kanban or a Scrum team on an agile board." This confirms that backlogs are used in at least two different agile methodologies within Workfront.
3. Adobe Workfront Documentation, "Workload Balancer overview": This page describes the Workload Balancer as a tool for "viewing the capacity of your resources and seeing how much of their time is allocated to work." Its application is for resource management in general, not a feature unique to the Scrum process.
Keep practicing
Take the free AD0-E911 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AD0-E911 practice questions
- Question 1Which element is defined as a reportable variable determined by the relationship between …
- Question 2A project manager needs to know the date that a task is likely to be finished based on th…
- Question 4The vice president of operations asks one of their project managers to create a Workfront…
- Question 5A project manager has assigned a task to a team. One of the members of the team wants to …
- Question 6A project manager would like to assign tasks across projects to a team without having to …
- Question 7When a project owner grants Contribute access on a project to a user with the same access…