AD0-E911 practice question 1 of 10
Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?
Full set: 95 questionsIn Adobe Workfront, the Condition is an automatically calculated, reportable variable that indicates the health of a project. Its value (e.g., On Target, At Risk, In Trouble) is determined by comparing the project's Planned Completion Date against its Projected Completion Date. The Projected Completion Date is itself influenced by the progress and estimated dates of tasks within the project. This direct relationship between planned and projected dates makes 'Condition' the correct answer for the variable that reflects the project's timeline health.
A. Status: This is a manually updated field by the project manager to indicate the current state of work (e.g., Current, On Hold, Complete), not an automatic calculation based on date variances.
C. Progress Status: This indicates how a project is progressing against its timeline based on task completion (e.g., On Time, Late, Ahead), not the variance between overall planned and projected completion dates.
1. Adobe Experience League Documentation - "Overview of Project Condition and Condition Type": This document explicitly states
"The Condition of a project indicates whether the project is on track to complete on time. Workfront calculates it by comparing the Planned Completion Date of the project with the Projected Completion Date of the project." (Section: "How Workfront calculates Project Condition").
2. Adobe Experience League Documentation - "Glossary of Adobe Workfront terminology":
Condition: "An indicator of the progress of a work item
in relation to the planned completion date. The condition is calculated by comparing the projected completion date of the work item with the planned completion date."
Status: "The attribute of a project
task
or issue that indicates its current state in the workflow (for example
New
In Progress
or Complete)." This confirms it reflects the workflow state
not a date calculation.
3. Adobe Experience League Documentation - "Overview of Project Progress Status": This document defines Progress Status as an indicator of whether the project is on time
late
or ahead. It clarifies
"Workfront calculates the Progress Status of a project by comparing the percent complete of the project with the percentage of the total duration that has passed." This is a different calculation than the one described in the question.
Keep practicing
Take the free AD0-E911 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AD0-E911 practice questions
- Question 2A project manager needs to know the date that a task is likely to be finished based on th…
- Question 3What is unique to a Scrum iteration?
- Question 4The vice president of operations asks one of their project managers to create a Workfront…
- Question 5A project manager has assigned a task to a team. One of the members of the team wants to …
- Question 6A project manager would like to assign tasks across projects to a team without having to …
- Question 7When a project owner grants Contribute access on a project to a user with the same access…