AD0-E911 practice question 1 of 10

Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?

Full set: 95 questions
Answer options
A: Status
B: Condition Correct answer
C: Progress Status
Correct Answer:
B. Condition
Explanation

In Adobe Workfront, the Condition is an automatically calculated, reportable variable that indicates the health of a project. Its value (e.g., On Target, At Risk, In Trouble) is determined by comparing the project's Planned Completion Date against its Projected Completion Date. The Projected Completion Date is itself influenced by the progress and estimated dates of tasks within the project. This direct relationship between planned and projected dates makes 'Condition' the correct answer for the variable that reflects the project's timeline health.

Why Incorrect

A. Status: This is a manually updated field by the project manager to indicate the current state of work (e.g., Current, On Hold, Complete), not an automatic calculation based on date variances.
C. Progress Status: This indicates how a project is progressing against its timeline based on task completion (e.g., On Time, Late, Ahead), not the variance between overall planned and projected completion dates.

References

1. Adobe Experience League Documentation - "Overview of Project Condition and Condition Type": This document explicitly states

"The Condition of a project indicates whether the project is on track to complete on time. Workfront calculates it by comparing the Planned Completion Date of the project with the Projected Completion Date of the project." (Section: "How Workfront calculates Project Condition").

2. Adobe Experience League Documentation - "Glossary of Adobe Workfront terminology":

Condition: "An indicator of the progress of a work item

in relation to the planned completion date. The condition is calculated by comparing the projected completion date of the work item with the planned completion date."

Status: "The attribute of a project

task

or issue that indicates its current state in the workflow (for example

New

In Progress

or Complete)." This confirms it reflects the workflow state

not a date calculation.

3. Adobe Experience League Documentation - "Overview of Project Progress Status": This document defines Progress Status as an indicator of whether the project is on time

late

or ahead. It clarifies

"Workfront calculates the Progress Status of a project by comparing the percent complete of the project with the percentage of the total duration that has passed." This is a different calculation than the one described in the question.

Scroll to Top