AGILE-FOUNDATION practice question 23 of 25

In Scrum, what answers the question ‘what can be done this sprint?’

Full set: 132 questions
Answer options
A: Daily scrum
B: Sprint review
C: Sprint planning Correct answer
D: Increment
Correct Answer:
C. Sprint planning
Explanation

Sprint Planning is the Scrum event that initiates the Sprint. It addresses two key topics: "Why is this Sprint valuable?" and "What can be done this Sprint?". During the second part of the meeting, the Development Team selects items from the Product Backlog they can complete within the Sprint. This selection process, in collaboration with the Product Owner, directly answers the question of what work can be accomplished. The outcome is the Sprint Backlog, which represents the plan for the Sprint.

Why Incorrect

A. The Daily Scrum is a 15-minute event for the Development Team to synchronize activities and create a plan for the next 24 hours, not the entire sprint.
B. The Sprint Review is held at the end of a Sprint to inspect the Increment and adapt the Product Backlog; it looks at what was done, not what can be done.
D. The Increment is the sum of all the Product Backlog items completed during a Sprint; it is the outcome of the work, not the planning of it.

References

- Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 9. "Sprint Planning addresses the following topics: Topic Two: What can be done this Sprint? ...the Developers select items from the Product Backlog to include in the current Sprint."

- AXELOS. (2015). PRINCE2 Agile®. The Stationery Office. Section 21.3.2, Sprint planning, p. 178. "The development team pulls work from the top of the product backlog... This answers the question ‘What can be done this Sprint?’"