AGILE-FOUNDATION practice question 24 of 25

What should be emphasized when tailoring the PRINCE2 Progress theme?

Full set: 132 questions
Answer options
A: Monitoring what is being delivered Correct answer
B: Tracking time and cost
C: Planning resources
D: Assessing the impact of risks
Correct Answer:
A. Monitoring what is being delivered
Explanation

In a PRINCE2 Agile context, the emphasis of the Progress theme shifts from traditional activity-based tracking to product-based tracking. The primary concern is the delivery of features and products that provide value. Agile techniques like burndown charts and Kanban boards focus on visualizing the flow of work and the completion of deliverables, making the monitoring of what is being delivered the central point of progress assessment.

Why Incorrect

B. Tracking time and cost are often fixed constraints (timeboxes, stable teams) in agile, with scope being the variable. The emphasis is on what is delivered within those constraints.
C. Planning resources is a planning activity, not a primary focus of progress monitoring, which is concerned with tracking performance against the plan.
D. Assessing the impact of risks is a core activity of the Risk theme, not the Progress theme, although risk management is integrated throughout the project.

References

AXELOS. (2015). PRINCE2 Agile®. The Stationery Office. Section 15.3.1, p. 103. "The emphasis for progress monitoring needs to be on what is being delivered... This is a subtle but important difference from a more traditional PRINCE2 project where the emphasis can be on monitoring the progress of activities."