AGILE-FOUNDATION practice question 24 of 25
What should be emphasized when tailoring the PRINCE2 Progress theme?
Full set: 132 questionsIn a PRINCE2 Agile context, the emphasis of the Progress theme shifts from traditional activity-based tracking to product-based tracking. The primary concern is the delivery of features and products that provide value. Agile techniques like burndown charts and Kanban boards focus on visualizing the flow of work and the completion of deliverables, making the monitoring of what is being delivered the central point of progress assessment.
B. Tracking time and cost are often fixed constraints (timeboxes, stable teams) in agile, with scope being the variable. The emphasis is on what is delivered within those constraints.
C. Planning resources is a planning activity, not a primary focus of progress monitoring, which is concerned with tracking performance against the plan.
D. Assessing the impact of risks is a core activity of the Risk theme, not the Progress theme, although risk management is integrated throughout the project.
AXELOS. (2015). PRINCE2 Agile®. The Stationery Office. Section 15.3.1, p. 103. "The emphasis for progress monitoring needs to be on what is being delivered... This is a subtle but important difference from a more traditional PRINCE2 project where the emphasis can be on monitoring the progress of activities."
Keep practicing
Take the free AGILE-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILE-FOUNDATION practice questions
- Question 1When tracking progress, which term describes using agile techniques at the delivery level…
- Question 2Which statement describes the Kanban approach?
- Question 3Which of the following is an example of 'being agile' rather than just ‘doing agile’?
- Question 4What is the purpose of the 'progress' practice?
- Question 5To help with prioritization, what is MOST important when understanding the difference bet…
- Question 6What is the MOST important when blending PRINCE2 Project Management with agile?