AGILE-FOUNDATION practice question 10 of 25
What information is NOT typically displayed on a burn chart?
Full set: 132 questionsA burn chart is a graphical representation of work left to do versus time. The vertical axis typically shows the amount of work remaining (e.g., in story points or hours), and the horizontal axis represents time (e.g., days or sprints). It includes a line for the planned rate of work completion and another for the actual work completed, allowing the team to track progress against the plan. Team working agreements are the set of norms, rules, or guidelines created by the team to govern their interactions and processes; this information is qualitative and not plotted on a burn chart.
A. Effort remaining is the primary data shown on the vertical axis of a burn-down chart, representing the work left to complete.
C. The actual amount of work done is plotted over time to show progress against the ideal or planned line.
D. The amount of time elapsed is the fundamental data for the horizontal axis, showing the timeline of the sprint or release.
AXELOS. (2015). PRINCE2 Agile® Foundation. The Stationery Office. Section 20.2.1, p. 158. "A burn chart shows the progress of a team... The vertical axis shows the amount of work to be done... The horizontal axis shows time."
AXELOS. (2015). PRINCE2 Agile® Foundation. The Stationery Office. Figure 20.1, p. 158. This figure explicitly shows 'Effort' on the Y-axis and 'Time' on the X-axis.
Keep practicing
Take the free AGILE-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILE-FOUNDATION practice questions
- Question 1When tracking progress, which term describes using agile techniques at the delivery level…
- Question 2Which statement describes the Kanban approach?
- Question 3Which of the following is an example of 'being agile' rather than just ‘doing agile’?
- Question 4What is the purpose of the 'progress' practice?
- Question 5To help with prioritization, what is MOST important when understanding the difference bet…
- Question 6What is the MOST important when blending PRINCE2 Project Management with agile?
