AGILE-FOUNDATION practice question 9 of 25

How are user inputs FIRST gathered in the 'quality' practice?

Full set: 132 questions
Answer options
A: As user stories in the product backlog Correct answer
B: As epic user stories in the project backlog
C: As the project Definition of Done in the quality management approach
D: As a quality control activity in the quality register
Correct Answer:
A. As user stories in the product backlog
Explanation

In PRINCE2 Agile, quality is primarily about meeting customer requirements and acceptance criteria. The initial inputs from users are captured as requirements, which are commonly expressed as user stories. These user stories, along with their associated acceptance criteria, are collected and prioritized in the product backlog. This forms the foundation of the quality practice, as delivering what is described in these stories to the agreed-upon standard (Definition of Done) is the measure of quality.

Why Incorrect

B. Epics are large, high-level user stories. While they are an input, the more granular user stories are the primary initial gathering format.
C. The Definition of Done is a quality standard applied to user stories; it is not the initial gathering of user requirements themselves.
D. A quality control activity is a check performed on a finished product or deliverable, not the initial gathering of user inputs.

References

AXELOS. (2018). PRINCE2 Agile® Foundation. TSO (The Stationery Office). Section 8.1, p. 65.

AXELOS. (2018). PRINCE2 Agile® Foundation. TSO (The Stationery Office). Section 13.2, p. 106.