AGILE-FOUNDATION practice question 13 of 25

When should PRINCE2 Agile be used?

Full set: 132 questions
Answer options
A: When a team is created to deliver a specific product Correct answer
B: When delivering an ongoing service to a customer
C: When an established team performs product maintenance
D: When simple requests to update a product are implemented
Correct Answer:
A. When a team is created to deliver a specific product
Explanation

PRINCE2 Agile is a project management method designed for projects, which are temporary undertakings to create a specific product or result. It is not intended for ongoing, business-as-usual (BAU) activities such as service delivery or routine maintenance. The scenario of creating a team to deliver a specific product perfectly describes a project, which is the correct context for applying PRINCE2 Agile.

Why Incorrect

B. Delivering an ongoing service is a continuous operational activity (BAU), not a project with a defined start and end.
C. Product maintenance by an established team is typically considered an ongoing operational task (BAU), not a temporary project structure.
D. Implementing simple update requests is usually handled as part of ongoing operations or a minor change process, not a formal project.

References

AXELOS. (2015). PRINCE2 Agile®. The Stationery Office. Section 3.1, p. 19. "PRINCE2 is a project management method... A project is a temporary organization that is created for the purpose of delivering one or more business products according to an agreed Business Case."